Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
280 N SUNNY COVE PL
Apply Date:
11/04/2024
Applicant:
Dana Petty
Description:
SFR MER1402370 T21-M0077 REV1 roof covering change (Model Master plan TC-MDP-0223-00506)

Permit Reviews

Permit Number - TC-MDP-1124-01265
Permit Status: Complete
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change (Model Master plan TC-MDP-0223-00506)
Start Date Submittal Complete Date Status  
01/30/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/03/2025 APPROVED Review Details
03/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/01/2025 APPROVED Review Details
11/07/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 11/14/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-1124-01265
Permit Status: Complete
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change (Model Master plan TC-MDP-0223-00506)
Date Description Comments
11/07/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
11/01/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
11/07/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
01/31/2025 Post-Installed Anchor Inspection Report is required.
11/07/2024 Post-Tension Inspection Report is required.
11/01/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
11/01/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
11/07/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-1124-01265
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change (Model Master plan TC-MDP-0223-00506)
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/12/2025 COT - RSPL - Backwater Valve Passed Underground plumbing is complete and connected to HCS. Backwater valve is installed between clean outs. Entire system is under a water test with no leaks. Okay to shade pipes and backfill trenches.
02/12/2025 COT - RSPL - Sewer Passed Underground plumbing is complete and connected to HCS. Backwater valve is installed between clean outs. Entire system is under a water test with no leaks. Okay to shade pipes and backfill trenches.
02/12/2025 COT - RSPL - Rough Soil Passed Underground plumbing is complete and connected to HCS. Backwater valve is installed between clean outs. Entire system is under a water test with no leaks. Okay to shade pipes and backfill trenches.
02/12/2025 COT - RSPL - Yard Water Line Passed Main water line is trenched and installed from meter box to house. System is under street pressure with no leaks. Okay to shade pipe and backfill trench.
02/19/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, masa clips and Simpson shear wall brackets are nailed to the form per plan requirements. Underground plumbing is properly wrapped with foam, shower and bath tub knock-outs are reinforced with rebar. Underground electrical is installed for kitchen island. Ufer ground is installed in bottom of footing of garage. Post tension cabling is evenly spaced. Okay to pour concrete for footings and slab.
02/19/2025 COT - RSBU - Preslab Passed Concrete forms are set, masa clips and Simpson shear wall brackets are nailed to the form per plan requirements. Underground plumbing is properly wrapped with foam, shower and bath tub knock-outs are reinforced with rebar. Underground electrical is installed for kitchen island. Ufer ground is installed in bottom of footing of garage. Post tension cabling is evenly spaced. Okay to pour concrete for footings and slab.
02/19/2025 COT - RSEL - Electrical Underground Passed Concrete forms are set, masa clips and Simpson shear wall brackets are nailed to the form per plan requirements. Underground plumbing is properly wrapped with foam, shower and bath tub knock-outs are reinforced with rebar. Underground electrical is installed for kitchen island. Ufer ground is installed in bottom of footing of garage. Post tension cabling is evenly spaced. Okay to pour concrete for footings and slab.
02/28/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Passed 2/28/25 ok to proceed to intermediate stage
02/28/2025 COT - RSBU - Roof Nailing Passed Passed 2/28/25 ok to proceed to intermediate stage
03/20/2025 COT - RSEL - Grounding/Bonding Passed
03/20/2025 BULD - Electrical Clearance Passed 20 March 25
TEP CLEARANCE: ECO
03/20/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
03/20/2025 COT - RSPL - Gas Pressure Test Passed
04/01/2025 COT - RSBU - Interior Shear Bracing Passed Passed 4/1/25 ok to tape
05/16/2025 COT - BULD - SWG Clearance Passed Passed 5/16/25 CLEARANCE SWG
05/22/2025 COT - RSEL - Electrical Final Passed
05/22/2025 COT - RSEL - Outdoor Lighting Passed
05/22/2025 COT - RSME - Mechanical Final Passed
05/22/2025 COT - RSPL - Plumbing Final Passed
05/22/2025 RSBU - Building Final Passed
05/22/2025 RSBU - Building Progress Passed
05/23/2025 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
153499 PT LOT 152 COMPLETE-2025-03-27_V1.PDF DOCUMENTS VIEW
LOT 152 SPECIAL INSPECTION CERTIFICATE REVISED-2025-01-28_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 152 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 152 SPECIAL INSPECTION CERTIFICATE-2024-11-04_V1.PDF DOCUMENTS VIEW