Permit: TC-MDP-1123-01831
Permit Details
Apply Date:
05/09/2024
Applicant:
Celina Rodriguez
Description:
SFR BT1465-130 T22-M0011
Permit Reviews
Permit Number - TC-MDP-1123-01831
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/10/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/14/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1123-01831
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
05/13/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/13/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
05/13/2024 | Post-Tension Inspection Report is required. |
05/13/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
05/13/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-1123-01831
Permit Status: Inspections complete
Permit Description: SFR BT1465-130 T22-M0011
Date | Description | Comments |
---|---|---|
11/21/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01831
Permit Description: SFR BT1465-130 T22-M0011
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/29/2024 | COT - RSPL - Rough Soil | Passed | ||
05/29/2024 | COT - RSPL - Sewer | Passed | ||
05/29/2024 | COT - RSPL - Yard Water Line | Passed | ||
06/07/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
06/07/2024 | COT - RSBU - Preslab | Passed | ||
06/07/2024 | COT - RSEL - Electrical Underground | Passed | ||
06/07/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
07/30/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/30/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/31/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/31/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
08/07/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
08/09/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 8/9/2024 | |
09/11/2024 | COT - BULD - SWG Clearance | Passed | Passed SW Gas clearance 9/11/2024 | |
10/22/2024 | COT - RSEL - Electrical Final | Passed | PASSED FINAL INSPECTION CLEARANCE ECO 10/22/24 | |
10/22/2024 | COT - RSEL - Outdoor Lighting | Passed | Passed outdoor lighting final 10/22/24 | |
10/22/2024 | COT - RSME - Mechanical Final | Passed | Passed mechanical final 10/22/24 | |
10/22/2024 | COT - RSPL - Plumbing Final | Passed | Passed plumbing final 10/22/24 | |
10/22/2024 | ENGR Engineering Final | Passed | Tree needs to be staked | |
10/22/2024 | RSBU - Building Final | Passed | PASSED FINAL INSPECTION 10/22/24 | |
10/22/2024 | RSBU - Building Progress | Passed | passed 10/22/24 |