Permit: TC-MDP-1123-01792
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
972 W SILVERLAKE RD
Address NEW:
972 W SILVERLAKE RD
Apply Date:
11/14/2023
Applicant:
Jose Quintero
Description:
SWDUPLEXM SUNSET MODEL DUPLEX 3-2 TRUSS REVIEW COMPLETE PREVIOUSLY APPROVED MODEL T20-00004
Permit Reviews
Permit Number - TC-MDP-1123-01792
Permit Status: Inspections complete
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2 TRUSS REVIEW COMPLETE
PREVIOUSLY APPROVED
MODEL T20-00004
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/14/2023 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 11/15/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-1123-01792
Permit Status: Inspections complete
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2 TRUSS REVIEW COMPLETE
PREVIOUSLY APPROVED
MODEL T20-00004
| Date | Description | Comments |
|---|---|---|
| 11/15/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01792
Permite Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2 TRUSS REVIEW COMPLETE
PREVIOUSLY APPROVED
MODEL T20-00004
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2023 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 04/12/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 04/12/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1123-01792
Permit Description: SWDUPLEXM SUNSET MODEL DUPLEX 3-2 TRUSS REVIEW COMPLETE
PREVIOUSLY APPROVED
MODEL T20-00004
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/06/2023 | COT - RSPL - Rough Soil | Passed | Approved. Okay to backfill. Shading required. 12/6/2023 | |
| 12/08/2023 | COT - RSBU - Preslab | Passed | Ok to place concrete. | |
| 12/14/2023 | COT - RSEL - Grounding/Bonding | Passed | Footings and slab have been poured..placed at contractor’s risk. | |
| 12/14/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footings and slab have been poured…contractor placed at own risk. | |
| 12/18/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 12/18/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 12/19/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 12/22/2023 | BULD - Electrical Clearance | Passed | 12/22/23: ECO TEP CLEARANCE for 972 W Silverlake RD unit 1 and unit 2 | |
| 12/22/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 01/26/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill shading required. 1/26/24 | |
| 04/10/2024 | COT - RSPL - Sewer | Passed | Two,four inch sewer lines from site to,main,sewer in roadway. Covered, compacted and asphalted. | |
| 04/12/2024 | ENGR Engineering Final | Passed | ||
| 04/12/2024 | RSBU - Building Progress | Passed | ||
| 04/12/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 04/18/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 04/19/2024 | COT - RSEL - Electrical Final | Passed | 4/18/24: weep screed clearance must be 4" above grade (not meeting clearance throughout), water heater T&P drain must terminate 6" above grade, water heaters missing pan per code P2801.6 and pan shall drain no less than 6" above grade, A/C condensate drain must be UV coated, Arc-fault breakers required at kitchen circuits and laundry circuit. Cut clean outs to grade. 4/19/24: corrections made. |
|
| 04/19/2024 | COT - RSME - Mechanical Final | Passed | 4/18/24: weep screed clearance must be 4" above grade (not meeting clearance throughout), water heater T&P drain must terminate 6" above grade, water heaters missing pan per code P2801.6 and pan shall drain no less than 6" above grade, A/C condensate drain must be UV coated, Arc-fault breakers required at kitchen circuits and laundry circuit. Cut clean outs to grade. 4/19/24: corrections made. |
|
| 04/19/2024 | COT - RSPL - Plumbing Final | Passed | 4/18/24: weep screed clearance must be 4" above grade (not meeting clearance throughout), water heater T&P drain must terminate 6" above grade, water heaters missing pan per code P2801.6 and pan shall drain no less than 6" above grade, A/C condensate drain must be UV coated, Arc-fault breakers required at kitchen circuits and laundry circuit. Cut clean outs to grade. 4/19/24: corrections made. |
|
| 04/19/2024 | RSBU - Building Final | Passed | 4/18/24: weep screed clearance must be 4" above grade (not meeting clearance throughout), water heater T&P drain must terminate 6" above grade, water heaters missing pan per code P2801.6 and pan shall drain no less than 6" above grade, A/C condensate drain must be UV coated, Arc-fault breakers required at kitchen circuits and laundry circuit. Cut clean outs to grade. 4/19/24: corrections made. |