Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
5963 E BENBURB LN
Apply Date:
12/19/2025
Applicant:
David Alcantar III
Description:
Blackhawk L021 Clark (Model Master Plan TC-MDP-1025-00679)

Permit Reviews

Permit Number - TC-MDP-1025-00691
Permit Status: Inspections complete
Permit Description: Blackhawk L021 Clark (Model Master Plan TC-MDP-1025-00679)
Start Date Submittal Complete Date Status  
01/07/2026 SITE FROM MODEL PERMIT - SUBDIVISION v.2 01/16/2026 APPROVED Review Details
01/23/2026 ADMINISTRATIVE v.3 01/23/2026 APPROVED Review Details
01/23/2026 ADMINISTRATIVE v.2 01/23/2026 REQUIRES RESUBMIT Review Details
12/23/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 01/02/2026 REQUIRES RESUBMIT Review Details
01/16/2026 ADMINISTRATIVE v.1 01/16/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1025-00691
Permit Status: Inspections complete
Permit Description: Blackhawk L021 Clark (Model Master Plan TC-MDP-1025-00679)
Total Outstanding Activity Conditions - 5
Date Name
01/23/2026 Post-Installed Anchor Inspection Report is required.
01/23/2026 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
10/29/2025 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
10/29/2025 Post-Tension Inspection Report is required.
10/29/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Conditions

Permit Number - TC-MDP-1025-00691
Permit Status: Inspections complete
Permit Description: Blackhawk L021 Clark (Model Master Plan TC-MDP-1025-00679)
Date Description Comments
01/16/2026 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
10/29/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
10/29/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1025-00691
Permit Description: Blackhawk L021 Clark (Model Master Plan TC-MDP-1025-00679)
Total Completed Inspections - 20
Date Description Inspector Results Comments
02/09/2026 COT - RSPL - Yard Water Line Passed 02/09/2026
Approved, holding under test from meter to riser with blue tracer. Okay to backfill with shading material.
02/10/2026 COT - RSPL - Rough Soil Passed 02/10/2026
Holding under test. Okay to backfill with shading material.
02/10/2026 COT - RSPL - Sewer Passed 02/10/2026
Holding under test. Okay to backfill with shading material.
02/18/2026 COT - RSBU - Preslab Passed 2.18.26
Approved
02/18/2026 COT - RSBU - Excavation/Rebar/Zoning Passed 2.18.26
Approved
02/18/2026 COT - RSEL - Electrical Underground Passed 2.18.26
Approved
02/27/2026 COT - RSBU - Roof Nailing Passed
03/06/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 03/06/2026
Corrections made to 2/27/26 inspection.
03/06/2026 BULD - Electrical Clearance Passed 03/06/2026
Approved clearance TEP ECO.
03/23/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 3.23.26
Approved
03/23/2026 COT - RSPL - Gas Pressure Test Passed
03/23/2026 RSBU - Building Progress Passed
04/02/2026 COT - RSBU - Interior Shear Bracing Passed 4.2.26
approved
05/05/2026 COT - BULD - SWG Clearance Passed 5.5.26
Approved - proceed
05/18/2026 RSBU - Building Final Passed
05/18/2026 COT - RSPL - Plumbing Final Passed
05/18/2026 COT - RSME - Mechanical Final Passed
05/18/2026 COT - RSEL - Outdoor Lighting Passed
05/18/2026 COT - RSEL - Electrical Final Passed
05/20/2026 ENGR Engineering Final Passed 5/20/26 - Site is complete in accordance with approved plans.