Permit: TC-MDP-1024-01245
Permit Details
Apply Date:
10/28/2024
Applicant:
Frank Maldonado
Description:
Model Duplex (Model master plan TC-MDP-0924-00989)
Permit Reviews
Permit Number - TC-MDP-1024-01245
Permit Status: Complete
Permit Description: Model Duplex (Model master plan TC-MDP-0924-00989)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/03/2025 | SITE FROM MODEL PERMIT - SUBDIVISION v.2 | 04/07/2025 | APPROVED |
| 06/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/23/2025 | APPROVED |
| 03/21/2025 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 03/24/2025 | REQUIRES RESUBMIT |
| 11/04/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 11/14/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-1024-01245
Permit Status: Complete
Permit Description: Model Duplex (Model master plan TC-MDP-0924-00989)
| Date | Description | Comments |
|---|---|---|
| 10/23/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 03/21/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 04/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 10/23/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 11/15/2024 | Full payment needed prior to issuance of CofO. | |
| 10/23/2024 | Post-Tension Inspection Report is required. | |
| 10/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 10/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 11/06/2024 | A Special Inspections Certificate, with both Part A and Part B completed, must be submitted and reviewed prior to issuance of this permit. | |
| 12/04/2024 | Prior to project being finalized applicant must provide documentation of a finalized plat. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01245
Permite Description: Model Duplex (Model master plan TC-MDP-0924-00989)
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2025 | COT - RSPL - Yard Water Line | N/A | Canceled | Canceled by contractor |
| 06/25/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 06/25/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 02/14/2025 | COT - RSBU - Roof Nailing | N/A | Canceled | Canceled by contractor |
| 11/26/2024 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | 11/26/24: Partial for UFER |
| 06/25/2025 | RSBU - Building Final | N/A | Partial Pass | Okay for level 4 TCO. Pending resolution of Sewer Backwater valve needed for C of O. |
| 06/25/2025 | ENGR Engineering Final | N/A | Partial Pass | Okay for level 4 TCO. Pending resolution of Sewer Backwater valve needed for C of O. Wedge curb wear in front drive needs repair. Slope adjacent to Storm water Channel needs to be decreased. Lower access path to back yard by 4” so slope into channel is not so steep. Send pictures for approval today. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01245
Permit Description: Model Duplex (Model master plan TC-MDP-0924-00989)
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2024 | COT - RSPL - Sewer | Passed | Pass | |
| 11/25/2024 | COT - RSPL - Rough Soil | Passed | pass | |
| 11/26/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11/26/24: reinforcement at footings and slab per plan ok to proceed with pour. | |
| 02/27/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Passed 2/27/25 | |
| 04/17/2025 | COT - RSPL - Yard Water Line | Passed | 4-17-25, main water line verified under test. Okay to backfill and continue with construction. | |
| 05/01/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 5-1-25, intermediate inspection approved. Okay to continue with construction. | |
| 05/14/2025 | COT - RSBU - Interior Shear Bracing | Passed | 5-14-25, shear bracing inspection approved. Okay for tape & texture. | |
| 05/30/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 06/03/2025 | BULD - Electrical Clearance | Passed | 5/30/25: Cover plates required at main panel dead front, bond bushing must be grounded. 6/3/25:ECO TEP CLEARANCE OK TO ENERGIZE |
|
| 06/25/2025 | COT - RSEL - Electrical Final | Passed | ||
| 06/25/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/25/2025 | COT - RSME - Mechanical Final | Passed | ||
| 06/25/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 06/25/2025 | RSBU - Building Progress | Passed | ||
| 06/25/2025 | COT - RSBU - Preslab | Passed | ||
| 06/25/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 06/25/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 08/25/2025 | RSBU - Building Final | Passed | ||
| 08/25/2025 | COT - RSPL - Backwater Valve | Passed | ||
| 08/27/2025 | ENGR Engineering Final | Passed |