Permit: TC-MDP-1024-01215
Permit Details
Apply Date:
10/15/2024
Applicant:
David Evans
Description:
Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Permit Reviews
Permit Number - TC-MDP-1024-01215
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/19/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 01/14/2025 | REQUIRES RESUBMIT |
| 10/21/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 11/14/2024 | REQUIRES RESUBMIT |
| 01/22/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 01/24/2025 | APPROVED |
| 11/19/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 12/14/2024 | REQUIRES RESUBMIT |
| 01/24/2025 | RESTAMP - RESIDENTIAL v.1 | 01/29/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-1024-01215
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
| Date | Description | Comments |
|---|---|---|
| 10/21/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 10/15/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 10/15/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/24/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01215
Permite Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 2/11/25 h25 clips missing at trusses, have framer re walk the exterior for missing nails. I marked the places. Re inspection required. |
| 06/24/2025 | ENGR Engineering Final | N/A | Not Ready | Utility room door will not close. Gravel needs to be even depth. It is not 2” by ROW sidewalk. Traffic cones need to be removed. Water meter pins are sticking out of sidewalk creating tripping hazard. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-1024-01215
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2025 | COT - RSPL - Rough Soil | Passed | 2/6/25 pass | |
| 02/07/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 2/7/25 pass | |
| 02/07/2025 | COT - RSBU - Preslab | Passed | 2/7/25 pass | |
| 02/11/2025 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | pass | |
| 02/11/2025 | COT - RSBU - Interior Shear Bracing | Passed | 2/11/25 pass | |
| 02/11/2025 | COT - RSBU - Roof Nailing | Passed | 2/11/25 pass | |
| 02/20/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 2/19/25 pass | |
| 03/05/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3-5-25, residential intermediate inspection approved. Okay to continue with construction. | |
| 05/13/2025 | COT - RSPL - Yard Water Line | Passed | 5-13-25, main water line verified under pressure-okay to backfill with shading materials. | |
| 05/13/2025 | COT - RSEL - Grounding/Bonding | Passed | 5-13-25, grounding/bonding approved. | |
| 05/19/2025 | BULD - Electrical Clearance | Passed | 5-19-25, panel is okay to be energized. ECO clearance issued to TEP. | |
| 06/03/2025 | COT - RSPL - Sewer | Passed | ||
| 06/18/2025 | RSBU - Building Final | Passed | 6-18-25: building final approved. | |
| 06/26/2025 | COT - RSME - Mechanical Final | Passed | ||
| 06/26/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/26/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 06/26/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 06/26/2025 | COT - RSEL - Electrical Final | Passed |