Permit: TC-MDP-1023-01670
Permit Details
Apply Date:
10/20/2023
Applicant:
Jorge Teran
Description:
Casas del Cerrito H35G Model Plan
Permit Reviews
Permit Number - TC-MDP-1023-01670
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/14/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/18/2024 | APPROVED |
10/20/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/30/2023 | REQUIRES RESUBMIT |
02/06/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 02/13/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-1023-01670
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/23/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-1023-01670
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Date | Description | Comments |
---|---|---|
06/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/23/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
04/23/2024 | Post-Tension Inspection Report is required. | |
09/11/2023 | Post-Tension Inspection Report is required. | |
04/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
10/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
10/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
10/20/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
09/11/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01670
Permite Description: Casas del Cerrito H35G Model Plan
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2024 | COT - RSEL - Grounding/Bonding | N/A | Not Applicable | |
04/23/2024 | RSBU - Building Progress | N/A | Not Applicable | |
07/05/2024 | ENGR Engineering Final | N/A | Not Ready | The west side of this property rear lot drainage needs to be moderately graded a little more to ensure that drainage will flow to the front of the yard. The air conditioning unit at the southwest corner of this property is propped up on a large rock on the north side of the pad. This pad should be constructed out of dirt compacted, and then the air conditioning unit placed onto it. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01670
Permit Description: Casas del Cerrito H35G Model Plan
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/29/2024 | COT - RSPL - Yard Water Line | Passed | ||
03/11/2024 | COT - RSPL - Rough Soil | Passed | Approved rough soil, okay to continue with pre-slab | |
03/19/2024 | BULD - Electrical Clearance | Passed | ||
03/19/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
03/19/2024 | COT - RSBU - Preslab | Passed | ||
03/19/2024 | COT - RSEL - Electrical Underground | Passed | ||
04/04/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
04/04/2024 | COT - RSBU - Roof Nailing | Passed | ||
04/23/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
04/23/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
05/01/2024 | COT - RSPL - Sewer | Passed | 5/1/24: Sewer line is connected to the underground plumbing line. Okay to shade pipes and backfill trench. | |
05/02/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
07/02/2024 | COT - BULD - SWG Clearance | Passed | Approved, SWG Clearance is required for the new gas meter | |
07/03/2024 | COT - RSEL - Outdoor Lighting | Passed | Outdoor lighting is properly installed and operational per the plan. | |
07/03/2024 | COT - RSME - Mechanical Final | Passed | Mechanical equipment is installed and operational. Dead front on electrical panel needs to be properly installed so breakers are aligned with edge of opening. All romex wire sleeves used for labeling circuits must be removed from inside of electrical panel. Clean-outs need to be cut down to grade. | |
07/09/2024 | COT - RSPL - Plumbing Final | Passed | ||
07/09/2024 | RSBU - Building Final | Passed | ||
07/09/2024 | COT - RSEL - Electrical Final | Passed | ||
07/10/2024 | ENGR Engineering Final | Passed |