Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
6422 S AMBARELLA DR
Apply Date:
10/17/2023
Applicant:
Celina Rodriguez
Description:
VC 1465-130

Permit Reviews

Permit Number - TC-MDP-1023-01620
Permit Status: Inspections complete
Permit Description: VC 1465-130
Start Date Submittal Complete Date Status  
10/17/2023 SITE FROM MODEL PERMIT - SUBDIVISION v.1 10/23/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-1023-01620
Permit Status: Inspections complete
Permit Description: VC 1465-130
Total Outstanding Activity Conditions - 5
Date Name
04/03/2023 Post-Tension Inspection Report is required.
04/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
08/11/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
10/17/2023 Post-Installed Anchor Inspection Report is required.
10/17/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-1023-01620
Permit Status: Inspections complete
Permit Description: VC 1465-130
Date Description Comments
10/23/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
08/11/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
10/13/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01620
Permite Description: VC 1465-130
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
12/22/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required Attic access requirements not met, missing 1.5" VTR for kitchen sink per plans. Insulation has been installed before passing intermediate. Remove ALL insulation from house.
01/02/2024 COT - RSBU - Interior Shear Bracing N/A Re-inspection required Cancelled per Karl.
1/2/24: no plans on site.
01/02/2024 BULD - Electrical Clearance N/A Not Ready 1/2/24: Not ready
03/06/2024 COT - RSME - Mechanical Final N/A Not Ready Mechanical vent in master not installed, landscaping grade
3/6/24: Not ready
03/06/2024 RSBU - Building Final N/A Not Ready Mechanical vent in master not installed, landscaping grade
3/6/24: Not ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-1023-01620
Permit Description: VC 1465-130
Total Completed Inspections - 20
Date Description Inspector Results Comments
11/07/2023 COT - RSPL - Rough Soil Passed
11/07/2023 COT - RSPL - Sewer Passed
11/07/2023 COT - RSPL - Yard Water Line Passed
11/09/2023 COT - RSEL - Electrical Underground Passed
11/09/2023 COT - RSEL - Grounding/Bonding Passed
11/13/2023 COT - RSBU - Preslab Passed
11/14/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
11/29/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 11/29/23: All items from the 11/24/23 have been corrected. Okay to proceed with exterior dry-in of walls and roof.
11/29/2023 COT - RSBU - Roof Nailing Passed 11/29/23: All items from the 11/24/23 have been corrected. Okay to proceed with exterior dry-in of walls and roof.
12/20/2023 COT - RSPL - Gas Pressure Test Passed
01/03/2024 COT - RSBU - Interior Shear Bracing Passed 1/3/2024. Approved.
01/08/2024 BULD - Electrical Clearance Passed
02/07/2024 COT - BULD - SWG Clearance Passed
03/01/2024 COT - RSEL - Electrical Final Passed
03/01/2024 COT - RSEL - Outdoor Lighting Passed
03/01/2024 COT - RSPL - Plumbing Final Passed
03/01/2024 RSBU - Building Progress Passed
03/08/2024 COT - RSME - Mechanical Final Passed
03/08/2024 RSBU - Building Final Passed
03/08/2024 ENGR Engineering Final Passed