Permit: TC-MDP-0925-00547
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
2956 N RICHEY BL UNIT 1
Address NEW:
2956 N RICHEY BL UNIT 1
Apply Date:
09/19/2025
Applicant:
David Evans
Description:
Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Permit Reviews
Permit Number - TC-MDP-0925-00547
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/22/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 11/04/2025 | APPROVED |
| 09/19/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 10/14/2025 | REQUIRES RESUBMIT |
| 11/04/2025 | RESTAMP - RESIDENTIAL v.1 | 11/04/2025 | APPROVED |
| 11/06/2025 | ADMINISTRATIVE v.1 | 11/06/2025 | APPROVED |
| 11/06/2025 | ADMINISTRATIVE v.2 | 11/06/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0925-00547
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
| Date | Description | Comments |
|---|---|---|
| 09/15/2025 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 09/15/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/15/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 10/01/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0925-00547
Permite Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled | |
| 03/25/2026 | COT - RSPL - Sewer | N/A | Re-inspection required | 3/25/26 Not ready, contractor has not finished work, about 15% complete;missing backwater valve per plan. |
| 05/29/2026 | RSBU - Building Progress | N/A | Not Applicable | |
| 05/29/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 05/29/2026 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 05/29/2026 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 05/29/2026 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | Electrician still wiring panels |
| 05/29/2026 | RSBU - Building Final | N/A | Re-inspection required | Electrician still wiring panels |
| 05/29/2026 | ENGR Engineering Final | N/A | Re-inspection required | 5/29/26 - Site plan indicated a PAG 206 apron and sidewalk at ROW, this is missing. Water service lines are exposed on the customer side of the meter, these need backfilled. Private sewer clean out (KN 3) is either missing or buried, this needs to be traffic rated if it's in the driveway. Private 2-way clean outs (KN 11) are missing or buried. Curb cut is supposed to be reduced to 14-0 (KN 4), this has not been done. Sidewalk connection ROW to building (KN 15)has been excluded. Electrical service panels are open with exposed wiring, not currently in a safe condition. These items need to be completed or a revised site plan showing the as-built conditions needs to be submitted to Planning and Development for review and approval. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0925-00547
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2025 | COT - RSPL - Rough Soil | Passed | ||
| 11/18/2025 | COT - RSBU - Preslab | Passed | ||
| 12/16/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 12/16/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 01/30/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Passed 1/30/26 | |
| 02/11/2026 | COT - RSBU - Interior Shear Bracing | Passed | 02/11/2026 5/8" type x common firewall on both sides. |
|
| 03/26/2026 | COT - RSPL - Sewer | Passed | 3/26/26 Passed, corrections made |
|
| 04/29/2026 | BULD - Electrical Clearance | Passed | Eco for units 1 and 2 Duplex |
|
| 05/05/2026 | COT - RSPL - Yard Water Line | Passed | 05/05/2026 Holding under test, okay to backfill with shading material. |
|
| 05/29/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Passed | |
| 05/29/2026 | COT - RSPL - Backwater Valve | Passed | Passed | |
| 06/02/2026 | COT - RSEL - Electrical Final | Passed | ||
| 06/01/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/02/2026 | COT - RSME - Mechanical Final | Passed | ||
| 06/02/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 06/03/2026 | RSBU - Building Final | Passed | 6/2/26: building final approved. CofO will not get issued until engineering final has been approved. | |
| 06/04/2026 | ENGR Engineering Final | Passed | Site issues have been corrected. Site is complete in accordance with approved plans. Okay for CofO. |