Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/19/2025
Applicant:
David Evans
Description:
Greenhill grande duplex (Model master plan TC-MDP-1223-01917)

Permit Reviews

Permit Number - TC-MDP-0925-00547
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Start Date Submittal Complete Date Status  
10/22/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 11/04/2025 APPROVED Review Details
09/19/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 10/14/2025 REQUIRES RESUBMIT Review Details
11/04/2025 RESTAMP - RESIDENTIAL v.1 11/04/2025 APPROVED Review Details
11/06/2025 ADMINISTRATIVE v.1 11/06/2025 APPROVED Review Details
11/06/2025 ADMINISTRATIVE v.2 11/06/2025 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0925-00547
Permit Status: Complete
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Date Description Comments
09/15/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
09/15/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
09/15/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
10/01/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0925-00547
Permite Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
01/20/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Canceled
03/25/2026 COT - RSPL - Sewer N/A Re-inspection required 3/25/26
Not ready, contractor has not finished work, about 15% complete;missing backwater valve per plan.
05/29/2026 RSBU - Building Progress N/A Not Applicable
05/29/2026 COT - BULD - SWG Clearance N/A Not Applicable
05/29/2026 COT - RSEL - Electrical Underground N/A Not Applicable
05/29/2026 COT - RSPL - Gas Pressure Test N/A Not Applicable
05/29/2026 COT - RSEL - Outdoor Lighting N/A Re-inspection required Electrician still wiring panels
05/29/2026 RSBU - Building Final N/A Re-inspection required Electrician still wiring panels
05/29/2026 ENGR Engineering Final N/A Re-inspection required 5/29/26 - Site plan indicated a PAG 206 apron and sidewalk at ROW, this is missing. Water service lines are exposed on the customer side of the meter, these need backfilled. Private sewer clean out (KN 3) is either missing or buried, this needs to be traffic rated if it's in the driveway. Private 2-way clean outs (KN 11) are missing or buried. Curb cut is supposed to be reduced to 14-0 (KN 4), this has not been done. Sidewalk connection ROW to building (KN 15)has been excluded. Electrical service panels are open with exposed wiring, not currently in a safe condition.
These items need to be completed or a revised site plan showing the as-built conditions needs to be submitted to Planning and Development for review and approval.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0925-00547
Permit Description: Greenhill grande duplex (Model master plan TC-MDP-1223-01917)
Total Completed Inspections - 17
Date Description Inspector Results Comments
11/13/2025 COT - RSPL - Rough Soil Passed
11/18/2025 COT - RSBU - Preslab Passed
12/16/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
12/16/2025 COT - RSBU - Roof Nailing Passed
01/30/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 1/30/26
02/11/2026 COT - RSBU - Interior Shear Bracing Passed 02/11/2026
5/8" type x common firewall on both sides.
03/26/2026 COT - RSPL - Sewer Passed 3/26/26
Passed, corrections made
04/29/2026 BULD - Electrical Clearance Passed Eco for units 1 and 2
Duplex
05/05/2026 COT - RSPL - Yard Water Line Passed 05/05/2026
Holding under test, okay to backfill with shading material.
05/29/2026 COT - RSBU - Excavation/Rebar/Zoning Passed Passed
05/29/2026 COT - RSPL - Backwater Valve Passed Passed
06/02/2026 COT - RSEL - Electrical Final Passed
06/01/2026 COT - RSEL - Outdoor Lighting Passed
06/02/2026 COT - RSME - Mechanical Final Passed
06/02/2026 COT - RSPL - Plumbing Final Passed
06/03/2026 RSBU - Building Final Passed 6/2/26: building final approved. CofO will not get issued until engineering final has been approved.
06/04/2026 ENGR Engineering Final Passed Site issues have been corrected. Site is complete in accordance with approved plans. Okay for CofO.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
LAYOUT1_V1.PDF DOCUMENTS VIEW