Permit: TC-MDP-0823-01469
Permit Details
Apply Date:
02/23/2024
Applicant:
Paul Schmidt
Description:
SFR F40F22 T22-M0026
Permit Reviews
Permit Number - TC-MDP-0823-01469
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/27/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 03/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0823-01469
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
Total Outstanding Activity Conditions - 7
Date | Name |
---|---|
02/27/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
03/08/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
03/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
03/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
03/08/2024 | Post-Installed Anchor Inspection Report is required. |
03/08/2024 | Post-Tension Inspection Report is required. |
03/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0823-01469
Permit Status: Inspections complete
Permit Description: SFR F40F22 T22-M0026
Date | Description | Comments |
---|---|---|
08/01/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/08/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01469
Permit Description: SFR F40F22 T22-M0026
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/15/2024 | COT - RSPL - Rough Soil | Passed | Main sewer line & Underground plumbing is installed and under a water test with no leaks. Okay to shade pipe, backfill trenches, and prepare for subsoil compaction for concrete slab on grade. | |
04/15/2024 | COT - RSPL - Sewer | Passed | Main sewer line & Underground plumbing is installed and under a water test with no leaks. Okay to shade pipe, backfill trenches, and prepare for subsoil compaction for concrete slab on grade. | |
04/15/2024 | COT - RSPL - Yard Water Line | Passed | Water line is connected to city main with water meter installed, blue tracer wire is wrapped around pipe from meter to house. Okay to shade pipe and backfill trench. | |
04/23/2024 | COT - RSBU - Preslab | Passed | ||
04/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
04/23/2024 | COT - RSEL - Electrical Underground | Passed | ||
05/10/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | All base plates are properly secured to concrete floor with A/B bolts, shot pins, or cut nails. All exterior shear walls are properly nailed to the studs per plans. H2.5 clips are properly secured to trusses and top plate. Okay to proceed with top out of plumbing and exterior dry in. | |
05/10/2024 | COT - RSBU - Roof Nailing | Passed | Trusses are properly installed and secured to top plate with H2.5 clips. Plywood sheathing is installed and nailed per plans and code. Okay to proceed with plumbing top out and roof dry-in. | |
06/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
06/10/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
06/10/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
06/10/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
07/01/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
08/07/2024 | COT - BULD - SWG Clearance | Passed | All locations for gas appliances have gas valves installed. SWG Clearance issued for gas meter to be installed. | |
08/30/2024 | RSBU - Building Progress | Passed | ||
09/09/2024 | COT - RSEL - Electrical Final | Passed | 9/9/24: Construction is complete. Okay to issue Certificate of Occupancy. | |
09/09/2024 | COT - RSEL - Outdoor Lighting | Passed | 9/9/24: Outdoor lighting is properly installed per plans and City regulations and fully operational. | |
09/09/2024 | COT - RSME - Mechanical Final | Passed | 9/9/24: Construction is complete. Okay to issue Certificate of Occupancy. | |
09/09/2024 | COT - RSPL - Plumbing Final | Passed | 9/9/24: Construction is complete. Okay to issue Certificate of Occupancy. | |
09/09/2024 | ENGR Engineering Final | Passed | Move in ready | |
09/09/2024 | RSBU - Building Final | Passed | 9/9/24: Construction is complete. Okay to issue Certificate of Occupancy. |