Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
04/22/2024
Applicant:
Description:
SFR RKM45R T21-M0093 (REVISION Delta 4)

Permit Reviews

Permit Number - TC-MDP-0823-01452
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Start Date Submittal Complete Date Status  
04/26/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 05/01/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0823-01452
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Activity Conditions - 5
Date Name
04/30/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/30/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/30/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/30/2024 Post-Tension Inspection Report is required.
04/30/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0823-01452
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Date Description Comments
08/23/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01452
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Completed Inspections - 21
Date Description Inspector Results Comments
06/05/2024 COT - RSPL - Rough Soil Passed Underground plumbing is properly connected to sewer line, green tracer wire is installed from clean outs to sewer connection, entire system is under a 10' water test with no leaks. Okay to shade pipes and backfill trenches.
06/05/2024 COT - RSPL - Sewer Passed Underground plumbing is properly connected to sewer line, green tracer wire is installed from clean outs to sewer connection, entire system is under a 10' water test with no leaks. Okay to shade pipes and backfill trenches.
06/05/2024 COT - RSPL - Yard Water Line Passed Main water supply line is connected to meter and under street pressure with no leaks. Blue tracer wire is installed on pipe from meter to house inlet. Okay to shade pipe and backfill trench.
06/24/2024 COT - RSEL - Electrical Underground Passed
06/24/2024 COT - RSBU - Preslab Passed
06/24/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
06/24/2024 COT - RSEL - Grounding/Bonding Passed
07/24/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Bottom plate is properly secured to concrete floor with titanium bolts, red heads, cut nails, shot pins, or masa clips. Shear wall clips and hold downs are properly nailed to studs and bolted to concrete floor through bottom plate. Plywood sheathing for shear walls are properly secured to studs per plan requirements. Okay to proceed with mechanical, electrical, and plumbing rough-in.
07/24/2024 COT - RSBU - Roof Nailing Passed Roof trusses are properly secured to top plate with nails and H2.5 clips. All bracing and rat runs are installed. Plywood sheathing for roof deck is properly nailed to trusses. Okay to proceed with mechanical, electrical, and plumbing rough-in.
08/23/2024 BULD - Electrical Clearance Passed Okay to energize panel. ECO Clearance issued to TEP for 12774 E Meagan Ridge Place.
08/26/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
08/26/2024 COT - RSPL - Gas Pressure Test Passed
09/13/2024 COT - RSBU - Interior Shear Bracing Passed Drywall is properly secured to studs per plan requirements of the drywall shear walls. Okay to proceed with tape, texture, and paint
10/23/2024 COT - BULD - SWG Clearance Passed Gas valves are installed in kitchen, laundry, attic, and garage for all gas appliances. Okay to proceed with gas meter installation and turn on. SWG Clearance issued.
11/20/2024 COT - RSEL - Electrical Final Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.
11/20/2024 COT - RSEL - Outdoor Lighting Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.
11/20/2024 COT - RSME - Mechanical Final Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.
11/20/2024 COT - RSPL - Plumbing Final Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.
11/20/2024 ENGR Engineering Final Passed CO Ready
11/20/2024 RSBU - Building Final Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.
11/20/2024 RSBU - Building Progress Passed 11-20-24, building ,mechanical, electrical, outdoor lighting, plumbing finals are all approved.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INPSECTION CERT-2024-04-22_V1.PDF DOCUMENTS VIEW