Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
08/09/2023
Applicant:
Celina Rodriguez
Description:
SFR BT2013-140 T22-M0036

Permit Reviews

Permit Number - TC-MDP-0823-01365
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Start Date Submittal Complete Date Status  
08/10/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 08/14/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0823-01365
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 5
Date Name
08/10/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/10/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/10/2023 Post-Installed Anchor Inspection Report is required.
08/14/2023 Post-Tension Inspection Report is required.
08/14/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0823-01365
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Date Description Comments
08/09/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01365
Permite Description: SFR BT2013-140 T22-M0036
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/07/2023 COT - RSPL - Backwater Valve N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0823-01365
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 21
Date Description Inspector Results Comments
09/07/2023 COT - RSPL - Yard Water Line Passed
09/07/2023 COT - RSPL - Sewer Passed
09/07/2023 COT - RSPL - Rough Soil Passed
09/15/2023 COT - RSBU - Preslab Passed
09/15/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
09/15/2023 COT - RSEL - Grounding/Bonding Passed
09/15/2023 COT - RSEL - Electrical Underground Passed
10/09/2023 COT - RSBU - Roof Nailing Passed
10/10/2023 COT - RSBU - Exterior Clips/Sheathing Passed
11/14/2023 BULD - Electrical Clearance Passed 11/14/23: TEP ECO
11/17/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
11/17/2023 COT - RSPL - Gas Pressure Test Passed
12/01/2023 COT - RSBU - Interior Shear Bracing Passed Interior shear wall sheet rock is properly installed and screwed off. Okay to tape and texture walls.
01/18/2024 COT - BULD - SWG Clearance Passed SWG for meter only
01/30/2024 COT - RSEL - Electrical Final Passed
01/30/2024 COT - RSEL - Outdoor Lighting Passed
01/30/2024 COT - RSME - Mechanical Final Passed
01/30/2024 COT - RSPL - Plumbing Final Passed
01/30/2024 RSBU - Building Progress Passed
01/30/2024 ENGR Engineering Final Passed
01/31/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA II 9 SIC-2023-08-09_V1.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 2 - LOT 9 START_V1.PDF DOCUMENTS VIEW
P21WP00207 FINAL ACCEPTANCE BTII_V1.PDF DOCUMENTS VIEW