Permit: TC-MDP-0726-00573
Permit Details
Status:
Inspections
Type:
Model Building Permit
Address:
9707 E PANOPEIA DR
Address NEW:
9707 E PANOPEIA DR
Apply Date:
07/15/2026
Applicant:
Celina Rodriguez
Description:
Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Permit Reviews
Permit Number - TC-MDP-0726-00573
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 07/23/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0726-00573
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 07/13/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 07/13/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/23/2026 | Prior to Final - Required Documents - Post-Installed Anchor Inspection Report is required. |
Conditions
Permit Number - TC-MDP-0726-00573
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
| Date | Description | Comments |
|---|---|---|
| 07/13/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 07/13/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0726-00573
Permite Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/19/2026 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | 8-19-26 footings must be a minimum of 12 inches will need to clear out loose dirt at north End* PT at stationary end should have a maximum of 12 inches exposed no more than. |
| 10/09/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | Dwv not on test. Missing ground screw at pancake box outside of first bedroom. Add Boca plate to 2" line kitchen sink. Add brace to 2" line above ceiling at laundry room. Secure exhaust duct at laundry room. Add supports to line sets. Primary room receptacle exceeding 12'. Add fha plate to bottom plate at primary bathroom. Secure exhaust fan in primary bathroom. Secure fresh air intake. Stopped inspection. Other items may apply. 10/9/2026 |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0726-00573
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2026 | COT - RSPL - Rough Soil | Passed | 8-11-26 Okay to backfill shading is required before. | |
| 08/11/2026 | COT - RSPL - Sewer | Passed | 8-11-26 Okay to backfill shading is required before. | |
| 08/11/2026 | COT - RSPL - Yard Water Line | Passed | 8-11-26 Okay to backfill shading is required before. | |
| 08/19/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 08/20/2026 | COT - RSBU - Preslab | Passed | 8-20-26 All corrections have been made | |
| 09/08/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 9-8-26 shot pins are required throughout the bottom floor did not mark all but some. OK to continue. Will check for shot pins during intermediate. | |
| 09/08/2026 | COT - RSBU - Roof Nailing | Passed | 9-8-26 shot pins are required throughout the bottom floor did not mark all but some. OK to continue. Will check for shot pins during intermediate. | |
| 09/25/2026 | BULD - Electrical Clearance | Passed | 9-25-26 ECO Clearance approved | |
| 10/09/2026 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/09/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 10/13/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10/13/2026 Corrections made, walked rest of upstairs. |