Permit Details

Status:
Inspections
Type:
Model Building Permit
Apply Date:
10/17/2024
Applicant:
Celina Rodriguez
Description:
Bella Tierra Phase 3 1745-130

Permit Reviews

Permit Number - TC-MDP-0724-00816
Permit Status: Inspections
Permit Description: Bella Tierra Phase 3 1745-130
Start Date Submittal Complete Date Status  
10/24/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 11/12/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0724-00816
Permit Status: Inspections
Permit Description: Bella Tierra Phase 3 1745-130
Total Outstanding Activity Conditions - 4
Date Name
07/25/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
10/28/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/28/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/28/2024 Post-Tension Inspection Report is required.

Conditions

Permit Number - TC-MDP-0724-00816
Permit Status: Inspections
Permit Description: Bella Tierra Phase 3 1745-130
Date Description Comments
07/25/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0724-00816
Permite Description: Bella Tierra Phase 3 1745-130
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
01/07/2025 COT - RSBU - Exterior Clips/Sheathing N/A Re-inspection required 12/31/24 LUS24's needed at 2x6 on covered back patio. Anchor bolts must be secured, have framer walk through and check.


01/07/25
1. All SW11 or greater shear wall require anchor bolts with .0229"x3"x3" plate washer.
2. Patio not built per plan; the east beam should be a 6"x8" and pocket into wall; plans also call for BC6 post caps SE and SW posts.
01/10/2025 COT - RSBU - Roof Nailing N/A Re-inspection required 01/10/25
1. Missing BC6 post caps.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0724-00816
Permit Description: Bella Tierra Phase 3 1745-130
Total Completed Inspections - 13
Date Description Inspector Results Comments
11/14/2024 COT - RSPL - Rough Soil Passed 11-14-24, sewer not connected. Underground plumbing and main water line approved. Okay to backfill but reschedule sewer connection when ready.
11/14/2024 COT - RSPL - Yard Water Line Passed 11-14-24, sewer not connected. Underground plumbing and main water line approved. Okay to backfill but reschedule sewer connection when ready.
12/04/2024 COT - RSPL - Sewer Passed 12/4/24: Underground plumbing is connected to main sewer line with green tracer wire. Okay to shade pipe and backfill trenches.
12/10/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 12-10-24, excavation/setbacks approved.
12/10/2024 COT - RSBU - Preslab Passed 12-10-24, preslab, underground electric, and bonding all approved. Okay to pour concrete.
12/10/2024 COT - RSEL - Electrical Underground Passed 12-10-24, preslab, underground electric, and bonding all approved. Okay to pour concrete.
12/10/2024 COT - RSEL - Grounding/Bonding Passed 12-10-24, preslab, underground electric, and grounding/bonding all approved. Okay to pour concrete.
01/10/2025 COT - RSBU - Interior Shear Bracing Passed 01/10/25
1. Missing BC6 post caps.
01/13/2025 COT - RSBU - Exterior Clips/Sheathing Passed 1/13/25: All issues from other inspections have been resolved and corrected. Okay to proceed with other work.
01/13/2025 COT - RSBU - Roof Nailing Passed 1/13/25: All issues from other inspections have been resolved and corrected. Okay to proceed with other work.
01/23/2025 BULD - Electrical Clearance Passed 1-23-25, panel approved to be energized. ECO clearance issued to TEP
02/05/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 2-5-25, residential intermediate inspection approved plans. Okay to continue with construction.
02/05/2025 COT - RSPL - Gas Pressure Test Passed 2-5-25, approved.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 3 - LOT 55 START_V1.PDF DOCUMENTS VIEW
BTIII 55 SIC-2024-10-17_V1.PDF DOCUMENTS VIEW