Permit: TC-MDP-0723-01260
Permit Details
Apply Date:
08/08/2023
Applicant:
Mark Alteri
Description:
PVCS1500 T22-M0040 SFR
Permit Reviews
Permit Number - TC-MDP-0723-01260
Permit Status: Complete
Permit Description: PVCS1500 T22-M0040 SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/09/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/11/2023 | APPROVED |
10/17/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/17/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0723-01260
Permit Status: Complete
Permit Description: PVCS1500 T22-M0040 SFR
Date | Description | Comments |
---|---|---|
08/09/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
10/17/2023 | Post-Tension Inspection Report is required. | |
08/09/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
08/11/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0723-01260
Permite Description: PVCS1500 T22-M0040 SFR
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/14/2023 | COT - RSPL - Gas Pressure Test | N/A | Canceled | Canceled per contractor. 12/14/2023 |
12/14/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled | Canceled per contractor. 12/14/2023 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0723-01260
Permit Description: PVCS1500 T22-M0040 SFR
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/01/2023 | COT - RSPL - Backwater Valve | Passed | ||
09/01/2023 | COT - RSPL - Rough Soil | Passed | ||
09/01/2023 | COT - RSPL - Sewer | Passed | ||
09/08/2023 | COT - RSEL - Electrical Underground | Passed | 9/8/23 passed per letter photo attached | |
09/08/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 9/8/23 passed per letter | |
09/08/2023 | COT - RSBU - Preslab | Passed | 9/8/23 passed per letter photo attached | |
09/08/2023 | COT - RSEL - Grounding/Bonding | Passed | 9/8/23 passed per letter | |
10/09/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
10/09/2023 | COT - RSBU - Roof Nailing | Passed | ||
11/21/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
12/11/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
12/19/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
12/20/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 12/20/23: Penetration in garage has been fire foamed. Gas line has been attached to Ufer ground. Anchor bolts have been added in shear wall of master bedroom. Okay to proceed with insulation and drywall installation. | |
01/10/2024 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
03/27/2024 | COT - BULD - SWG Clearance | Passed | ||
03/27/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
03/27/2024 | RSBU - Building Progress | Passed | ||
03/27/2024 | ENGR Engineering Final | Passed | ||
04/01/2024 | COT - RSEL - Electrical Final | Passed | 4-1-24: Construction, mechanical, plumbing, and electrical are complete. Mechanical, plumbing, and electrical fixtures are installed and operational. AFCI breakers are installed in electrical panel for all circuits. GFCI outlets are installed in kitchen, laundry, bathrooms, and garage. Okay to issue Certificate of Occupancy once all other departments have signed off permit. | |
04/01/2024 | COT - RSME - Mechanical Final | Passed | 4-1-24: Construction, mechanical, plumbing, and electrical are complete. Mechanical, plumbing, and electrical fixtures are installed and operational. AFCI breakers are installed in electrical panel for all circuits. GFCI outlets are installed in kitchen, laundry, bathrooms, and garage. Okay to issue Certificate of Occupancy once all other departments have signed off permit. | |
04/01/2024 | COT - RSPL - Plumbing Final | Passed | 4-1-24: Construction, mechanical, plumbing, and electrical are complete. Mechanical, plumbing, and electrical fixtures are installed and operational. AFCI breakers are installed in electrical panel for all circuits. GFCI outlets are installed in kitchen, laundry, bathrooms, and garage. Okay to issue Certificate of Occupancy once all other departments have signed off permit. | |
04/01/2024 | COT - RSPL - Yard Water Line | Passed | 4/1/24: Water riser has been moved to the front corner of garage on side of house. | |
04/01/2024 | RSBU - Building Final | Passed | 4-1-24: Construction, mechanical, plumbing, and electrical are complete. Mechanical, plumbing, and electrical fixtures are installed and operational. AFCI breakers are installed in electrical panel for all circuits. GFCI outlets are installed in kitchen, laundry, bathrooms, and garage. Okay to issue Certificate of Occupancy once all other departments have signed off permit. |