Permit: TC-MDP-0625-00324
Permit Details
Status:
Inspections
Type:
Model Building Permit
Address:
5740 S NOGALES HY
Address NEW:
5740 S NOGALES HY
Apply Date:
06/06/2025
Applicant:
Jorge Navarro
Description:
Duplex (Model master plan TC-MDP-0724-00807)
Permit Reviews
Permit Number - TC-MDP-0625-00324
Permit Status: Inspections
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/05/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 09/19/2025 | REQUIRES RESUBMIT |
| 12/05/2025 | ADMINISTRATIVE v.1 | 12/05/2025 | REQUIRES RESUBMIT |
| 08/07/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 08/07/2025 | REQUIRES RESUBMIT |
| 11/14/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.5 | 11/20/2025 | APPROVED |
| 02/18/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/20/2026 | APPROVED |
| 11/05/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 11/12/2025 | REQUIRES RESUBMIT |
| 06/10/2025 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 06/26/2025 | REQUIRES RESUBMIT |
| 01/22/2026 | SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.1 | 01/30/2026 | APPROVED |
| 11/20/2025 | RESTAMP - RESIDENTIAL v.1 | 12/08/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0625-00324
Permit Status: Inspections
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
| Date | Description | Comments |
|---|---|---|
| 06/10/2025 | The plan submitted shows to be for a duplex BLDG 6 Units 11 & 12. The location 5740 S Nogales Hy does not have BLDG 6 attached to the address and a pre issuance addressing condition has been placed on permit. Please contact Pima County Addressing at addressing@pima.gov or 520-724-9512 to verify/add the BLDG number. An address change request is required to have the bldg added to this permit. In addition, if the BLDG and units end up different from the ones specified on your site plan and resubmittal may be required as well. | |
| 06/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 06/03/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 06/24/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0625-00324
Permite Description: Duplex (Model master plan TC-MDP-0724-00807)
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2026 | COT - RSPL - Rough Soil | N/A | Partial Pass | Partial pass. Building 6. Units 11 and 12. Sleeve has been provide as requested. Pre slab is approved per building 6 units 11 and 12. Okay for concrete placement. Pre slab inspection will be open again. Prior to next inspection. 2/23/2026 |
| 03/05/2026 | RSBU - Building Progress | N/A | Partial Pass | 03/05/2026 CMU wall final lift for Bldg 6 Unit 11 & 12. Partial pending other unit wall lifts. |
| 04/03/2026 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | 4-3-26: per workers on site, units in question are not ready for intermediate inspection. |
| 05/27/2026 | COT - RSPL - Sewer | N/A | Partial Pass | 5/27/26: Pressure test and piping completed per approved plans. As-built drawings will be required to show the actual location of sewer runs as installed throughout the development. Approved to backfill with the contingency that as-built drawings are submitted prior to final inspection. |
| 06/02/2026 | ENGR Engineering Final | N/A | Not Applicable | Inspection was called in error (was for water line), but I ended up talking to the owner/developer on phone about the inspections needed on the DP so that the project could go smoothly with a higher success rate. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0625-00324
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/12/2026 | COT - RSBU - Preslab | Passed | 02/12/2026 Duplex Unit 11 & 12. Approved per site plan, foundation details. Okay for concrete placement. |
|
| 02/12/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 02/12/2026 Duplex Unit 11 & 12. Approved per site plan, foundation details. Okay for concrete placement. |
|
| 03/31/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 04/03/2026 | COT - RSBU - Roof Nailing | Passed | 4/3/26 Inspected and Passed on 31 March 26. |
|
| 04/10/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 04/10/2026 Approved per plan, Unit 11 & 12 duplex. |
|
| 05/27/2026 | COT - RSEL - Grounding/Bonding | Passed | 5-27-26: Building 6-grounding/bonding for unit's 11 & 12 approved. |