Inspection Status: Partial Pass
Inspection History: COT - RSPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 02/19/2026 |
COT - RSPL - Rough Soil |
|
Partial Pass |
2-19-26: underground plumbing for unit's 11 & 12 approved. Okay to backfill using shading materials. Provide a 4" sleeve for charlotte piping penetrating cmu stem wall at both units. Provide a picture of each prior to grouting stem wall. |
| 02/23/2026 |
COT - RSPL - Rough Soil |
|
Partial Pass |
Partial pass. Building 6. Units 11 and 12. Sleeve has been provide as requested. Pre slab is approved per building 6 units 11 and 12. Okay for concrete placement. Pre slab inspection will be open again. Prior to next inspection. 2/23/2026 |