Permit Details

Status:
Inspections
Type:
Model Building Permit
Apply Date:
06/06/2025
Applicant:
Jorge Navarro
Description:
Duplex (Model master plan TC-MDP-0724-00807)

Permit Reviews

Permit Number - TC-MDP-0625-00322
Permit Status: Inspections
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
Start Date Submittal Complete Date Status  
12/05/2025 ADMINISTRATIVE v.1 12/05/2025 REQUIRES RESUBMIT Review Details
02/18/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/20/2026 APPROVED Review Details
09/05/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 09/19/2025 REQUIRES RESUBMIT Review Details
11/14/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.5 11/20/2025 APPROVED Review Details
08/07/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 08/07/2025 REQUIRES RESUBMIT Review Details
06/10/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 06/26/2025 REQUIRES RESUBMIT Review Details
11/04/2025 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 11/10/2025 REQUIRES RESUBMIT Review Details
11/20/2025 RESTAMP - RESIDENTIAL v.1 12/05/2025 APPROVED Review Details
01/22/2026 SITE FROM MODEL TEMPLATE INFILL BUILDERS REVISION v.1 01/30/2026 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0625-00322
Permit Status: Inspections
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
Date Description Comments
06/10/2025 The plan submitted shows to be for a duplex BLDG 4 Units 7 & 8. The location 5740 S Nogales Hy does not have BLDG 4 attached to the address and a pre issuance addressing condition has been placed on permit. Please contact Pima County Addressing at addressing@pima.gov or 520-724-9512 to verify/add the BLDG number. An address change request is required to have the bldg number added to this permit. In addition, if the BLDG and units end up different from the ones specified on your site plan and resubmittal may be required as well.
06/03/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
06/03/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/24/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0625-00322
Permite Description: Duplex (Model master plan TC-MDP-0724-00807)
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
02/24/2026 COT - RSBU - Excavation/Rebar/Zoning N/A Partial Pass 2-24-26: reinforcement for stem wall at unit's 7 & 8 verified per plans. Okay to grout at 1'.
04/08/2026 COT - RSBU - Masonry Pregrout N/A Partial Pass Building 4 unit 7 & 8 perimeter wall inspection at 8'
05/27/2026 COT - RSPL - Sewer N/A Partial Pass 5/27/26: Pressure test and piping completed per approved plans. As-built drawings will be required to show the actual location of sewer runs as installed throughout the development. Approved to backfill with the contingency that as-built drawings are submitted prior to final inspection.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0625-00322
Permit Description: Duplex (Model master plan TC-MDP-0724-00807)
Total Completed Inspections - 7
Date Description Inspector Results Comments
03/09/2026 COT - RSPL - Rough Soil Passed 03/09/2026
Okay to backfill with shading material.
03/18/2026 COT - RSBU - Preslab Passed 03/18/2026
Approved per plan. Okay for concrete placement.
04/01/2026 RSBU - Building Progress Passed next lift approved 4.1.26
04/15/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 04/15/2026
Approved per plan. Added shot pins on interior sill plates 6" from edges at marked locations.
04/27/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed O4/27/2026
Verified added foam to top plate penetrations and nail plate to protect DWV pipe.
05/27/2026 COT - RSEL - Grounding/Bonding Passed 5-27-26: Building 4-grounding/bonding for unit's 7 & 8 approved.
06/02/2026 COT - RSPL - Yard Water Line Passed

Documents

File Name Document Type  
TRUSS CALCULATION_V1.PDF DOCUMENTS VIEW
APPROVED - TD-DEV_0824-00228_ DEVELOPMENT PACKAGE_FINAL 4_V3 - STAMPED 11.03.2025_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
SITE DEVELOPMENT SHEET UNITS 7 - 8 REV_V1.PDF DOCUMENTS VIEW
11_12_SITE_PLAN_TC-MDP-0625-00322_BLDG 4 UNITS 7 - 8__V3_V4.PDF DOCUMENTS VIEW
CONS-11_11_MODEL_CONSTRUCTION DOCUMENTS BDLG 4__V2_V3.PDF DOCUMENTS VIEW