Permit Reviews

Permit Number - TC-MDP-0624-00739
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Start Date Submittal Complete Date Status  
07/22/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/30/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0624-00739
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Activity Conditions - 6
Date Name
06/24/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/30/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/30/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/30/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/30/2024 Post-Tension Inspection Report is required.
07/30/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0624-00739
Permit Status: Inspections complete
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Date Description Comments
06/24/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/30/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00739
Permite Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
10/04/2024 COT - RSBU - Roof Nailing N/A Re-inspection required 10/4/24: Anchor bolts missing at garage perimeter wall per detail 8/S4.1, RSP4 missing on east side of home exterior wall, Shear wall anchor bolt spacing not per plan. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 10/4/24: Anchor bolts missing at garage perimeter wall per detail 8/S4.1, RSP4 missing on east side of home exterior wall, Shear wall anchor bolt spacing not per plan. STOPPED INSPECTION MORE ITEMS MAY BE ADDED
12/06/2024 COT - RSBU - Interior Shear Bracing N/A Re-inspection required 12/6/24 Walk in closet in bathroom is not to schedule
02/19/2025 ENGR Engineering Final N/A Not Ready CO Ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00739
Permit Description: SFR RKM45R T21-M0093 (REVISION Delta 4)
Total Completed Inspections - 22
Date Description Inspector Results Comments
09/03/2024 COT - RSPL - Backwater Valve Passed Okay to backfill. Shading required. 9/3/2024
09/03/2024 COT - RSPL - Rough Soil Passed Okay to backfill. Shading required. 9/3/2024
09/03/2024 COT - RSPL - Sewer Passed Okay to backfill. Shading required. 9/3/2024
09/03/2024 COT - RSPL - Yard Water Line Passed Okay to backfill. Shading required. 9/3/2024
09/13/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Okay to pour concrete for footings and slab. Ufer ground is in place. Underground electrical for kitchen island is installed.
09/13/2024 COT - RSBU - Preslab Passed Okay to pour concrete for footings and slab. Ufer ground is in place. Underground electrical for kitchen island is installed.
09/13/2024 COT - RSEL - Electrical Underground Passed Okay to pour concrete for footings and slab. Ufer ground is in place. Underground electrical for kitchen island is installed.
10/11/2024 COT - RSBU - Roof Nailing Passed 10/9/24: Anchor bolts have been installed in shear wall and garage perimeter wall. RSP Clips have been added where missing. Okay to proceed with rough-in.
10/11/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 10/9/24: Anchor bolts have been installed in shear wall and garage perimeter wall. RSP Clips have been added where missing. Okay to proceed with rough-in.
11/14/2024 COT - RSEL - Grounding/Bonding Passed 11-14-24, approved.
11/14/2024 COT - RSPL - Gas Pressure Test Passed 11-15-24, approved
11/15/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 11-15-24, items from previous inspection have been corrected. Intermediate approved. okay to continue with construction.
11/15/2024 BULD - Electrical Clearance Passed 11-15-24, panel approved to be energized.
12/09/2024 COT - RSBU - Interior Shear Bracing Passed 12-9-24, interior shear verified as per approved plans, okay to tape & texture drywall.
01/31/2025 COT - BULD - SWG Clearance Passed 1/31/25 approval for SWG clearance
02/06/2025 COT - RSEL - Electrical Final Passed Passed final 2/6/25 CLEARANCE ECO
02/06/2025 COT - RSEL - Outdoor Lighting Passed Passed final 2/6/25
02/06/2025 COT - RSME - Mechanical Final Passed Passed final 2/6/25
02/06/2025 COT - RSPL - Plumbing Final Passed Passed final 2/6/25
02/06/2025 RSBU - Building Final Passed Passed final 2/6/25 CLEARANCE ECO
02/06/2025 RSBU - Building Progress Passed Passed final 2/6/25
02/20/2025 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT.-2024-07-18_V1.PDF DOCUMENTS VIEW