Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
06/04/2024
Applicant:
Andrea Flood
Description:
SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)

Permit Reviews

Permit Number - TC-MDP-0624-00713
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Start Date Submittal Complete Date Status  
09/05/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 09/12/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0624-00713
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Outstanding Activity Conditions - 6
Date Name
06/06/2024 Post-Tension Inspection Report is required.
06/06/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
09/11/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
09/11/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
09/11/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/11/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0624-00713
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Date Description Comments
06/06/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
09/11/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00713
Permite Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
03/06/2025 COT - RSEL - Electrical Final N/A Re-inspection required 6 Mar 25
Not ready
03/06/2025 COT - RSME - Mechanical Final N/A Re-inspection required 6 Mar 25
Not ready
03/06/2025 COT - RSPL - Plumbing Final N/A Re-inspection required 6 Mar 25
Not ready
03/06/2025 RSBU - Building Final N/A Re-inspection required 6 Mar 25
Not ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00713
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Completed Inspections - 22
Date Description Inspector Results Comments
10/01/2024 COT - RSPL - Yard Water Line Passed
10/01/2024 COT - RSPL - Sewer Passed
10/01/2024 COT - RSPL - Rough Soil Passed
10/01/2024 COT - RSPL - Backwater Valve Passed
10/10/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 10/10/24 passed.
10/10/2024 COT - RSBU - Preslab Passed 10/10/24 passed.
10/10/2024 COT - RSEL - Electrical Underground Passed 10/10/24 PASS
10/10/2024 COT - RSEL - Grounding/Bonding Passed 10/10/24 PASS
11/06/2024 COT - RSBU - Roof Nailing Passed 11-6-24: All items noted have been corrected, okay to proceed with rough in.
11/06/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 11-6-24: All items noted have been corrected, okay to proceed with rough in.
12/10/2024 COT - RSPL - Gas Pressure Test Passed 12-10-24, gas pressure test verified at 15 psi.
12/16/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 12-16-24, intermediate inspection approved plans. Ok to continue with construction.
12/17/2024 BULD - Electrical Clearance Passed 12/17/24 TEP clearance ECO.
01/07/2025 COT - RSBU - Interior Shear Bracing Passed Passed 1/7/25 ok to tape
02/26/2025 COT - BULD - SWG Clearance Passed 26 FEB 25
Southwest gas clearance: SWG
03/06/2025 COT - RSEL - Outdoor Lighting Passed 6 Mar 25
Not ready
03/06/2025 RSBU - Building Progress Passed 6 Mar 25
Not ready
03/10/2025 COT - RSEL - Electrical Final Passed 10 March 25
Pass
03/10/2025 COT - RSME - Mechanical Final Passed 10 March 25
Pass
03/10/2025 COT - RSPL - Plumbing Final Passed 10 March 25
Pass
03/10/2025 RSBU - Building Final Passed 10 March 25
Pass
04/11/2025 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW