Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0624-00710
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12703 E LAUREN CANYON PL
Address NEW:
12703 E LAUREN CANYON PL
Apply Date:
06/06/2024
Applicant:
Description:
SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Permit Reviews
Permit Number - TC-MDP-0624-00710
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/07/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/10/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0624-00710
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 06/06/2024 | Post-Tension Inspection Report is required. |
| 06/06/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 06/07/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 06/07/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 06/07/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 06/07/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0624-00710
Permit Status: Inspections complete
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
| Date | Description | Comments |
|---|---|---|
| 06/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/07/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0624-00710
Permit Description: SFR RKM45M T21-M0092 (Revision 2 structural cals and pages)
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/11/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 07/11/2024 | COT - RSPL - Sewer | Passed | ||
| 07/11/2024 | COT - RSPL - Rough Soil | Passed | ||
| 07/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 07/23/2024 | COT - RSBU - Preslab | Passed | ||
| 07/23/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 07/23/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 08/14/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly installed and nailed to top plate, all trusses have H2.5 clips nailed to them. Plywood sheathing is properly secured to roof trusses with nails per plan and code requirements. Okay to proceed with rough-in work. | |
| 08/14/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Shear wall hold down are properly secured with nails and interior shear walls are secured with nails and titan bolts to the concrete floor. Plywood sheathing on shear walls are properly secured with nails per plan requirements. Exterior and interior walls are secured to concrete floor with masa clips, titan bolts, j-bolts, or shot pins. All straps are properly placed and secured with nails. Diagonal bracing is properly installed and nailed to each stud. Okay to proceed with rough-in work. | |
| 09/17/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/17/2024 | |
| 09/20/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 09/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 10/07/2024 | COT - RSBU - Interior Shear Bracing | Passed | Drywall properly secured to studs for interior shear walls per plan. Okay to proceed with tape, texture, and paint. | |
| 12/03/2024 | COT - BULD - SWG Clearance | Passed | 12-3-24, approved for Southwest gas connection. | |
| 12/10/2024 | COT - RSEL - Outdoor Lighting | Passed | 12-10-24, outdoor lighting approved. | |
| 12/13/2024 | COT - RSEL - Electrical Final | Passed | 12/13/24 pass | |
| 12/13/2024 | COT - RSME - Mechanical Final | Passed | 12/13/24 pass | |
| 12/13/2024 | COT - RSPL - Plumbing Final | Passed | 12/13/24 pass | |
| 12/13/2024 | ENGR Engineering Final | Passed | CO Ready | |
| 12/13/2024 | RSBU - Building Final | Passed | 12/13/24 pass | |
| 12/13/2024 | RSBU - Building Progress | Passed |