Permit: TC-MDP-0623-01157
Permit Details
Apply Date:
07/07/2023
Applicant:
Stephanie Bebee
Description:
SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Permit Reviews
Permit Number - TC-MDP-0623-01157
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/22/2023 | APPROVED |
07/07/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 07/11/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0623-01157
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Date | Description | Comments |
---|---|---|
07/07/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
06/09/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/11/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0623-01157
Permit Description: SFR CVPLAN2.5 T22-M0062 V2 Structural changes
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/04/2023 | COT - RSPL - Yard Water Line | Passed | ||
08/04/2023 | COT - RSPL - Sewer | Passed | ||
08/04/2023 | COT - RSPL - Rough Soil | Passed | ||
08/04/2023 | COT - RSPL - Backwater Valve | Passed | ||
08/14/2023 | COT - RSBU - Preslab | Passed | Ufer ground is in place, forms are set with post-tension cables, subsoil is properly compacted, plumbing pipes are properly wrapped with foam, and all shear wall clips are in place. Okay to pour concrete for monolithic concrete slab. | |
08/14/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Ufer ground is in place, forms are set with post-tension cables, subsoil is properly compacted, plumbing pipes are properly wrapped with foam, and all shear wall clips are in place. Underground electrical is in place for kitchen island. Okay to pour concrete for monolithic concrete slab. | |
08/14/2023 | COT - RSEL - Grounding/Bonding | Passed | Ufer ground is in place, forms are set with post-tension cables, subsoil is properly compacted, plumbing pipes are properly wrapped with foam, and all shear wall clips are in place. Okay to pour concrete for monolithic concrete slab. | |
08/14/2023 | COT - RSEL - Electrical Underground | Passed | Ufer ground is in place, forms are set with post-tension cables, subsoil is properly compacted, plumbing pipes are properly wrapped with foam, and all shear wall clips are in place. Underground electrical is in place for kitchen island. Okay to pour concrete for monolithic concrete slab. | |
09/15/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
09/15/2023 | COT - RSBU - Roof Nailing | Passed | ||
11/06/2023 | BULD - Electrical Clearance | Passed | Electrical panel is properly installed, conduit sweep from meter box to transformer is in place. ECO Electrical Clearance issued for unit. Okay to energize power system. | |
11/17/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
11/17/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
12/08/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
02/20/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
02/20/2024 | COT - RSEL - Electrical Final | Passed | ||
02/20/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
02/20/2024 | RSBU - Building Progress | Passed | ||
02/21/2024 | ENGR Engineering Final | Passed | ||
02/22/2024 | COT - RSME - Mechanical Final | Passed | ||
02/22/2024 | COT - RSPL - Plumbing Final | Passed | ||