Permit: TC-MDP-0526-00338
Permit Details
Status:
Approved - Awaiting Customer Attention
Type:
Model Building Permit
Address:
120 W KELSO ST
Address NEW:
120 W KELSO ST
Apply Date:
05/08/2026
Applicant:
Description:
New 2BD 1BA Single Unit Model 100 (Model Master Plan TC-MDP-0326-00103)
Permit Reviews
Permit Number - TC-MDP-0526-00338
Permit Status: Approved - awaiting customer attention
Permit Description: New 2BD 1BA Single Unit Model 100 (Model Master Plan TC-MDP-0326-00103)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.4 | 07/17/2026 | APPROVED |
| 05/21/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 06/05/2026 | REQUIRES RESUBMIT |
| 07/17/2026 | ADMINISTRATIVE v.1 | 07/17/2026 | REQUIRES RESUBMIT |
| 06/25/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.3 | 07/16/2026 | REQUIRES RESUBMIT |
| 05/15/2026 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 05/15/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-MDP-0526-00338
Permit Status: Approved - awaiting customer attention
Permit Description: New 2BD 1BA Single Unit Model 100 (Model Master Plan TC-MDP-0326-00103)
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 06/25/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 06/25/2026 | MANUAL J |
| 06/25/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Conditions
Permit Number - TC-MDP-0526-00338
Permit Status: Approved - awaiting customer attention
Permit Description: New 2BD 1BA Single Unit Model 100 (Model Master Plan TC-MDP-0326-00103)
| Date | Description | Comments |
|---|---|---|
| 06/25/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |