Permit: TC-MDP-0524-00562
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6148 E BLACK CAVIAR PL
Address NEW:
6148 E BLACK CAVIAR PL
Apply Date:
05/01/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30M Model Plan
Permit Reviews
Permit Number - TC-MDP-0524-00562
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/02/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/13/2024 | APPROVED |
| 08/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/28/2025 | APPROVED |
| 07/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/18/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0524-00562
Permit Status: Inspections complete
Permit Description: Blackhawk H30M Model Plan
| Date | Description | Comments |
|---|---|---|
| 05/13/2024 | The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account. | |
| 05/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 05/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 05/01/2024 | Post-Tension Inspection Report is required. | |
| 05/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 05/08/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 05/08/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00562
Permit Description: Blackhawk H30M Model Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2025 | COT - RSPL - Rough Soil | Passed | ||
| 05/15/2025 | COT - RSPL - Sewer | Passed | ||
| 05/15/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 05/22/2025 | BULD - Electrical Clearance | Passed | 5-22-25, panel okay to be energized. ECO clearance issued to TEP. | |
| 05/22/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 5-22-25, excavation/reinforcement/setbacks and preslab verified per plans. Okay to pour concrete. | |
| 05/22/2025 | COT - RSBU - Preslab | Passed | 5-22-25, excavation/reinforcement/setbacks and preslab verified per plans. Okay to pour concrete. | |
| 05/22/2025 | COT - RSEL - Electrical Underground | Passed | 5-22-25, electrical underground approved. | |
| 06/09/2025 | COT - RSBU - Roof Nailing | Passed | 6-9-25: roof nailing approved. | |
| 06/17/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 06/27/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 06/27/2025 | COT - RSPL - Gas Pressure Test | Passed | ||
| 07/03/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 7/3/2025 | |
| 07/24/2025 | COT - RSBU - Interior Shear Bracing | Passed | 7.24.25 Fastener schedule at shear walls meets or exceed requirements. Ok to proceed. |
|
| 10/22/2025 | COT - BULD - SWG Clearance | Passed | 10.22.2025 Clearance to SWG. |
|
| 10/22/2025 | COT - RSEL - Electrical Final | Passed | ||
| 10/22/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/22/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 10/22/2025 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. Engineering is okay for CofO. | |
| 10/22/2025 | RSBU - Building Progress | Passed | ||
| 10/28/2025 | COT - RSME - Mechanical Final | Passed | 10.28.2025 Corrections made to prior inspection on 10.22.2025. |
|
| 10/28/2025 | RSBU - Building Final | Passed | 10.28.2025 Corrections made to prior inspection on 10.22.2025. |