Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0524-00553
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
10633 E ROSY MARBLE DR
Address NEW:
10633 E ROSY MARBLE DR
Apply Date:
05/01/2024
Applicant:
Dana Petty
Description:
SFR MER1502320 T21-M0070 REV1 roof covering change
Permit Reviews
Permit Number - TC-MDP-0524-00553
Permit Status: Complete
Permit Description: SFR MER1502320 T21-M0070 REV1 roof covering change
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/25/2025 | APPROVED |
| 11/07/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/07/2024 | APPROVED |
| 05/02/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/09/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0524-00553
Permit Status: Complete
Permit Description: SFR MER1502320 T21-M0070 REV1 roof covering change
| Date | Description | Comments |
|---|---|---|
| 05/03/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 05/03/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 05/03/2024 | Post-Tension Inspection Report is required. | |
| 05/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 05/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0524-00553
Permite Description: SFR MER1502320 T21-M0070 REV1 roof covering change
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2024 | COT - RSPL - Backwater Valve | N/A | Not Applicable | Not Applicable--No backwater valve shown on civil plan. Okay to proceed. |
| 10/07/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 10/4/24: no plans in house. Roof needs to be checked throughout several panels loose. |
| 10/07/2024 | COT - RSBU - Roof Nailing | N/A | Re-inspection required | 10/4/24: no plans in house. Roof needs to be checked throughout several panels loose. |
| 11/13/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | Missing address label |
| 11/13/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 11/13/24. FAIL. Improper blocking at four gang light switch. Use a 2 x 6 on its side. Missing light switch or receptacle at primary bathroom. Missing H2 five clips at Bering wall between bedroom and dining room. Another failed inspection will result in a reinspection fee. |
| 12/03/2024 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | G2 wall needs 4" blocking on edges, 3/8" from seams throughout, bedroom 3 closet panel has only 2 screws, falling off wall. Reinspect required 12/3/24 |
| 11/13/2024 | RSBU - Building Progress | N/A | Re-inspection required | 11/13/24. FAIL. Improper blocking at four gang light switch. Use a 2 x 6 on its side. Missing light switch or receptacle at primary bathroom. Missing H2 five clips at Bering wall between bedroom and dining room. Another failed inspection will result in a reinspection fee. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0524-00553
Permit Description: SFR MER1502320 T21-M0070 REV1 roof covering change
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 09/05/2024 | COT - RSPL - Sewer | Passed | ||
| 09/05/2024 | COT - RSPL - Rough Soil | Passed | ||
| 09/13/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 09/13/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 09/16/2024 | COT - RSBU - Preslab | Passed | ||
| 09/16/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 10/08/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/08/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 11/12/2024 | COT - RSPL - Gas Pressure Test | Passed | 11-12-24, gas pressure test verified at 15psi. | |
| 11/15/2024 | BULD - Electrical Clearance | Passed | 11-15-24, panel approved to be energized. | |
| 11/15/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 11-15-24, items from previous inspection have been corrected. | |
| 12/05/2024 | COT - RSBU - Interior Shear Bracing | Passed | Corrections were made. 12/5/2024 | |
| 01/31/2025 | COT - BULD - SWG Clearance | Passed | 1-31-25, approved-okay for Southwest gas to install meter. Clearance sent. | |
| 02/12/2025 | RSBU - Building Progress | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. | |
| 02/12/2025 | COT - RSEL - Electrical Final | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. | |
| 02/12/2025 | COT - RSEL - Outdoor Lighting | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. | |
| 02/12/2025 | COT - RSME - Mechanical Final | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. | |
| 02/12/2025 | COT - RSPL - Plumbing Final | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. | |
| 02/12/2025 | ENGR Engineering Final | Passed | ||
| 02/12/2025 | RSBU - Building Final | Passed | Construction is complete per plans. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Smoke detectors are installed and tied together. Okay to issue Certificate of Occupancy. |