Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
07/20/2023
Applicant:
Daria Hopkins
Description:
SFR MERI156021 T21-M0063

Permit Reviews

Permit Number - TC-MDP-0523-01015
Permit Status: Complete
Permit Description: SFR MERI156021 T21-M0063
Start Date Submittal Complete Date Status  
07/20/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 07/25/2023 APPROVED Review Details
08/28/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/28/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0523-01015
Permit Status: Complete
Permit Description: SFR MERI156021 T21-M0063
Date Description Comments
07/20/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/20/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/28/2024 Post-Tension Inspection Report is required.
05/11/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/28/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
07/20/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
07/21/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0523-01015
Permite Description: SFR MERI156021 T21-M0063
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
01/16/2024 COT - RSBU - Interior Shear Bracing N/A Re-inspection required 1/16/24: north wall in garage nailing not per schedule (studs are spaced 16" o.c, over span on nailing), nail schedule in no bedroom closet not per plan, nailing not per schedule throughout. No plans on site.
03/15/2024 COT - RSEL - Electrical Final N/A Canceled 3/15/24: canceled per contractor
03/15/2024 COT - RSEL - Outdoor Lighting N/A Canceled 3/15/24: canceled per contractor
03/15/2024 COT - RSME - Mechanical Final N/A Canceled 3/15/24: canceled per contractor
03/15/2024 COT - RSPL - Plumbing Final N/A Canceled 3/15/24: canceled per contractor
03/15/2024 RSBU - Building Final N/A Canceled 3/15/24: canceled per contractor
03/15/2024 RSBU - Building Progress N/A Canceled 3/15/24: canceled per contractor

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0523-01015
Permit Description: SFR MERI156021 T21-M0063
Total Completed Inspections - 21
Date Description Inspector Results Comments
09/29/2023 COT - RSPL - Rough Soil Passed
09/29/2023 COT - RSPL - Sewer Passed
09/29/2023 COT - RSPL - Yard Water Line Passed
10/06/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
10/06/2023 COT - RSBU - Preslab Passed
10/06/2023 COT - RSEL - Electrical Underground Passed
10/06/2023 COT - RSEL - Grounding/Bonding Passed
11/01/2023 COT - RSBU - Roof Nailing Passed
11/01/2023 COT - RSBU - Exterior Clips/Sheathing Passed
12/06/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Mechanical, electrical, and plumbing rough-in are complete. Okay to proceed with installation of insulation and drywall.
12/06/2023 BULD - Electrical Clearance Passed TEP ECO Clearance issued. okay to energize system.
12/06/2023 COT - RSPL - Gas Pressure Test Passed Gas lines are under 15# of air pressure and holding. Okay to proceed.
01/18/2024 COT - RSBU - Interior Shear Bracing Passed
03/12/2024 COT - BULD - SWG Clearance Passed SWG for meter only
03/15/2024 ENGR Engineering Final Passed
03/18/2024 COT - RSEL - Electrical Final Passed
03/18/2024 COT - RSEL - Outdoor Lighting Passed
03/18/2024 COT - RSME - Mechanical Final Passed
03/18/2024 COT - RSPL - Plumbing Final Passed
03/18/2024 RSBU - Building Final Passed
03/18/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
LOT 55 FINAL SPECIAL INSPECTION CERTIFICATE-2024-08-27_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 55 APPLICATION_V1.PDF DOCUMENTS VIEW
LOT 55 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 55 SPECIAL INSPECTION CERTIFICATE-2023-07-20_V1.PDF DOCUMENTS VIEW