Permit: TC-MDP-0425-00267
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
2701 S OAKENSHIELD WY
Address NEW:
2701 S OAKENSHIELD WY
Apply Date:
04/29/2025
Applicant:
Chris Irby
Description:
1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Permit Reviews
Permit Number - TC-MDP-0425-00267
Permit Status: Complete
Permit Description: 1453T Ireland
We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/25/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/25/2025 | APPROVED |
| 05/05/2025 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/13/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0425-00267
Permit Status: Complete
Permit Description: 1453T Ireland
We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
| Date | Description | Comments |
|---|---|---|
| 05/05/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 04/29/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/29/2025 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 04/29/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 04/29/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0425-00267
Permite Description: 1453T Ireland
We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | COT - RSEL - Electrical Underground | N/A | Not Applicable | site does not run underground electric |
| 07/24/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | Per notes. 3,5,6. Support gas lines 1st floor at every 8'. Receptacle I kitchen exceeds 2' from range. 7/24/2025 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0425-00267
Permit Description: 1453T Ireland
We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2025 | BULD - Electrical Clearance | Passed | Ready for temp power CLEARANCE ECO | |
| 06/18/2025 | COT - RSPL - Rough Soil | Passed | Passed 6/18/25 ok to backfill | |
| 06/18/2025 | COT - RSPL - Sewer | Passed | Passed 6/18/25 ok to backfill | |
| 06/18/2025 | COT - RSPL - Yard Water Line | Passed | Passed 6/18/25 ok to backfill | |
| 06/23/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Passed 6/23/25 ok to pour concrete | |
| 06/23/2025 | COT - RSBU - Preslab | Passed | Passed 6/23/25 ok to pour concrete | |
| 07/08/2025 | COT - RSBU - Roof Nailing | Passed | Passed 7/8/25 | |
| 07/23/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 07/23/2025 | COT - RSPL - Gas Pressure Test | Passed | ||
| 07/24/2025 | RSBU - Building Progress | Passed | ||
| 07/24/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/29/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 08/15/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed 8/15/25 | |
| 09/18/2025 | COT - RSEL - Outdoor Lighting | Passed | 9.18.25 APPROVED |
|
| 09/18/2025 | COT - BULD - SWG Clearance | Passed | 9.18.25 APPROVED |
|
| 09/18/2025 | COT - RSEL - Electrical Final | Passed | 9.18.25 APPROVED |
|
| 09/18/2025 | COT - RSME - Mechanical Final | Passed | 9.18.25 APPROVED |
|
| 09/18/2025 | COT - RSPL - Plumbing Final | Passed | 9.18.25 APPROVED |
|
| 09/18/2025 | RSBU - Building Final | Passed | 9.18.25 APPROVED |
|
| 09/24/2025 | ENGR Engineering Final | Passed | Site is clean and accessible, in accordance with plans. |