Permit Reviews

Permit Number - TC-MDP-0424-00520
Permit Status: Complete
Permit Description: SFR 500 Coolidge Model Plan La Escalera
Start Date Submittal Complete Date Status  
03/27/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/01/2025 APPROVED Review Details
06/06/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 06/07/2024 APPROVED Review Details
02/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/26/2025 REQUIRES RESUBMIT Review Details
03/05/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/10/2025 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0424-00520
Permit Status: Complete
Permit Description: SFR 500 Coolidge Model Plan La Escalera
Date Description Comments
06/07/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/07/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/07/2024 Post-Tension Inspection Report is required.
04/25/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/25/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
02/25/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
06/07/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0424-00520
Permite Description: SFR 500 Coolidge Model Plan La Escalera
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
11/15/2024 COT - BULD - SWG Clearance N/A Not Applicable 11-15-24, home contains no gas
11/15/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable 11-15-24, residence contains no gas appliances
11/21/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Partial Pass 11-21-24, with regards to the missing wall receptacle in primary bedroom submit a letter documenting code requirements from Austin electric and a schematic for electrical plan. Okay to proceed at own risk.
11/15/2024 COT - RSBU - Roof Nailing N/A Re-inspection required 11-15-24, roof is weighed down with tiles. I am unable to verify roof nailing. Therefore, provide a letter stating that roof nailing was nailed per approved plans or remove all tiles and reschedule an inspection.Also, pancake box for coach lights at garage are overfilled. Box is rated for 6 cubic inches and it contains 2 14/2 awg wires.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0424-00520
Permit Description: SFR 500 Coolidge Model Plan La Escalera
Total Completed Inspections - 20
Date Description Inspector Results Comments
08/15/2024 COT - RSPL - Backwater Valve Passed
08/15/2024 COT - RSPL - Rough Soil Passed
08/15/2024 COT - RSPL - Sewer Passed
08/15/2024 COT - RSPL - Yard Water Line Passed
08/29/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
08/29/2024 COT - RSBU - Preslab Passed
08/29/2024 COT - RSEL - Electrical Underground Passed
08/29/2024 COT - RSEL - Grounding/Bonding Passed
11/15/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 11-15-24, items from previous inspection have been corrected.
12/27/2024 COT - RSBU - Interior Shear Bracing Passed 12/27/24 passed ok to tape
03/12/2025 BULD - Electrical Clearance Passed Ready for power Clearance ECO
04/15/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed letter received
04/15/2025 COT - RSBU - Roof Nailing Passed passed
04/15/2025 COT - RSEL - Electrical Final Passed Passed final 4/15/25
04/15/2025 COT - RSME - Mechanical Final Passed Passed final 4/15/25
04/15/2025 COT - RSEL - Outdoor Lighting Passed Passed final 4/15/25
04/15/2025 COT - RSPL - Plumbing Final Passed Passed final 4/15/25
04/15/2025 ENGR Engineering Final Passed
04/15/2025 RSBU - Building Final Passed Passed final 4/15/25
04/15/2025 RSBU - Building Progress Passed Passed final 4/15/25

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
LOT 44 SIC-2025-03-26_V1.PDF DOCUMENTS VIEW
LOT 44 SIC-2025-03-04_V2.PDF DOCUMENTS VIEW
USE - PATTISON SOILS REPORT 1.25.2022_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
PHASE 1 LOT 44 PLOT PLAN_V1.PDF DOCUMENTS VIEW
PHASE 1A LOT 44 SIC-2024-06-05_V1.PDF DOCUMENTS VIEW