Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00517
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
9628 E HARKES DR
Address NEW:
9628 E HARKES DR
Apply Date:
05/28/2024
Applicant:
Brianna Quiroz
Description:
Eisenhower Model Plan La Escalera
Permit Reviews
Permit Number - TC-MDP-0424-00517
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/25/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/28/2025 | APPROVED |
| 05/30/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/03/2024 | APPROVED |
| 04/02/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/03/2025 | APPROVED |
| 03/27/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/01/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0424-00517
Permit Status: Complete
Permit Description: Eisenhower Model Plan La Escalera
| Date | Description | Comments |
|---|---|---|
| 06/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 06/03/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 06/03/2024 | Post-Tension Inspection Report is required. | |
| 04/25/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/25/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 06/03/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 06/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0424-00517
Permite Description: Eisenhower Model Plan La Escalera
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | 11-26-24, not applicable |
| 11/26/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | 11-26-24, not applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0424-00517
Permit Description: Eisenhower Model Plan La Escalera
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2024 | COT - RSPL - Backwater Valve | Passed | Okay to backfill. Shading required. 8/14/2024 | |
| 08/14/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 8/14/2024 | |
| 08/14/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 8/14/2024 | |
| 08/14/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 8/14/2024 | |
| 08/27/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 08/27/2024 | COT - RSBU - Preslab | Passed | ||
| 08/27/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 08/27/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 09/13/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Okay to proceed with rough-in of mechanical, electrical, and plumbing. | |
| 09/13/2024 | COT - RSBU - Roof Nailing | Passed | Okay to proceed with rough-in of mechanical, electrical, and plumbing. | |
| 11/08/2024 | BULD - Electrical Clearance | Passed | ECO CLEARANCE ISSUED. | |
| 12/31/2024 | COT - RSBU - Interior Shear Bracing | Passed | Passed, ok to tape 12/31/24 | |
| 05/06/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/06/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 05/06/2025 | COT - RSME - Mechanical Final | Passed | ||
| 05/06/2025 | ENGR Engineering Final | Passed | ||
| 05/06/2025 | RSBU - Building Progress | Passed | ||
| 05/09/2025 | RSBU - Building Final | Passed | 5/8/25 corrections made | |
| 05/09/2025 | COT - RSPL - Plumbing Final | Passed | 5/8/25 corrections made | |
| 05/09/2025 | COT - RSEL - Electrical Final | Passed | 5/8/25 corrections made |