Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00494
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
1841 S MATH QUIZ DR
Address NEW:
1841 S MATH QUIZ DR
Apply Date:
07/29/2024
Applicant:
Mark Alteri
Description:
SFR CVPLAN3 T22-M0044
Permit Reviews
Permit Number - TC-MDP-0424-00494
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2024 | APPROVED |
| 07/31/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/07/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0424-00494
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
| Date | Description | Comments |
|---|---|---|
| 08/06/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 08/06/2024 | Post-Tension Inspection Report is required. | |
| 04/17/2024 | Please submit Sewer Receipt. Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0424-00494
Permit Description: SFR CVPLAN3 T22-M0044
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 08/28/2024 | COT - RSPL - Sewer | Passed | ||
| 08/28/2024 | COT - RSPL - Rough Soil | Passed | ||
| 09/05/2024 | COT - RSBU - Preslab | Passed | ||
| 09/05/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 09/05/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 09/05/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/10/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/10/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 11/01/2024 | BULD - Electrical Clearance | Passed | ||
| 11/13/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is under 15psi of air pressure with no leaks. Okay to proceed with work. | |
| 11/13/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in complete per plan. Okay to proceed with installation of insulation and drywall. | |
| 12/13/2024 | COT - RSBU - Interior Shear Bracing | Passed | 12/13/24 shear wall is to schedule, pass | |
| 02/11/2025 | COT - BULD - SWG Clearance | Passed | ||
| 02/14/2025 | COT - RSEL - Electrical Final | Passed | 2-14-25, electrical final approved. | |
| 02/14/2025 | COT - RSEL - Outdoor Lighting | Passed | 2-14-25, outdoor lighting approved | |
| 02/14/2025 | COT - RSME - Mechanical Final | Passed | 2-14-25, mechanical final approved. | |
| 02/14/2025 | RSBU - Building Progress | Passed | ||
| 02/18/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 02/18/2025 | RSBU - Building Final | Passed | ||
| 02/25/2025 | ENGR Engineering Final | Passed |