Permit Details

Status:
Inspections
Type:
Model Building Permit
Apply Date:
10/04/2024
Applicant:
Description:
SFR RKK35L T21-M0084 REVISION-Structural changes

Permit Reviews

Permit Number - TC-MDP-0424-00490
Permit Status: Inspections
Permit Description: SFR RKK35L T21-M0084 REVISION-Structural changes
Start Date Submittal Complete Date Status  
10/07/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 10/10/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0424-00490
Permit Status: Inspections
Permit Description: SFR RKK35L T21-M0084 REVISION-Structural changes
Total Outstanding Activity Conditions - 7
Date Name
04/17/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
10/08/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
10/08/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/08/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/08/2024 Post-Tension Inspection Report is required.
10/08/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
10/08/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0424-00490
Permit Status: Inspections
Permit Description: SFR RKK35L T21-M0084 REVISION-Structural changes
Date Description Comments
10/07/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/17/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0424-00490
Permite Description: SFR RKK35L T21-M0084 REVISION-Structural changes
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
12/19/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required 12-19-24, shear walls not per schedule; missing nails in several areas throughout & over penetrated. See chapter 6 of the IRC for details. Loose anchor bolts throughout, several A-35's are missing nails or are not nailed flush to top plate. STOPPED INSPECTION, ADDITIONAL ITEMS MAY BE NOTED.
12/19/2024 COT - RSBU - Roof Nailing N/A Re-inspection required 12-19-24, provide ladder to inspect roof nailing.
01/24/2025 BULD - Electrical Clearance N/A Re-inspection required Breakers missing, open holes in dead front.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0424-00490
Permit Description: SFR RKK35L T21-M0084 REVISION-Structural changes
Total Completed Inspections - 20
Date Description Inspector Results Comments
11/26/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 11-26-24, underground plumbing, sewer, main water line, grounding/bonding approved
11/26/2024 COT - RSBU - Preslab Passed 11-26-24, underground plumbing, preslab, sewer, main water line, grounding/bonding approved. Okay to pour concrete
11/26/2024 COT - RSEL - Electrical Underground Passed 11-26-24, electrical underground approved
11/26/2024 COT - RSEL - Grounding/Bonding Passed 11-26-24, grounding/bonding approved
11/26/2024 COT - RSPL - Rough Soil Passed 11-26-24, underground plumbing, main water line, grounding/bonding approved
11/26/2024 COT - RSPL - Sewer Passed 11-26-24, underground plumbing, sewer, main water line, grounding/bonding approved
11/26/2024 COT - RSPL - Yard Water Line Passed 11-26-24, underground plumbing, sewer, main water line, grounding/bonding approved
01/07/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 1/7/25 corrections made
01/07/2025 COT - RSBU - Roof Nailing Passed 1/7/25 corrections made
01/24/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation.
01/27/2025 COT - RSPL - Gas Pressure Test Passed 1/27/25 pass
01/31/2025 BULD - Electrical Clearance Passed 1/31/25 approval for TEP ECO clearance
02/11/2025 COT - RSBU - Interior Shear Bracing Passed Passed interior shear bracing 2/11/25
03/26/2025 COT - BULD - SWG Clearance Passed 26 March 25
Southwest gas clearance: SWG
04/10/2025 COT - RSEL - Electrical Final Passed
04/10/2025 COT - RSEL - Outdoor Lighting Passed
04/10/2025 COT - RSME - Mechanical Final Passed
04/10/2025 COT - RSPL - Plumbing Final Passed
04/10/2025 RSBU - Building Final Passed
04/10/2025 ENGR Engineering Final Passed Site is good. C of O ready.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INPSECTION CERT-2024-10-04_V1.PDF DOCUMENTS VIEW