Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9781 E GRAY HAWK DR
Apply Date:
04/17/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35E Model Plan

Permit Reviews

Permit Number - TC-MDP-0424-00459
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35E Model Plan
Start Date Submittal Complete Date Status  
04/19/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 05/02/2024 APPROVED Review Details
09/16/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/17/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0424-00459
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35E Model Plan
Total Outstanding Activity Conditions - 1
Date Name
04/17/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - TC-MDP-0424-00459
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35E Model Plan
Date Description Comments
04/19/2024 Post-Installed Anchor Inspection Report is required.
04/19/2024 Post-Tension Inspection Report is required.
04/17/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/19/2024 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00459
Permit Description: Casas del Cerrito H35E Model Plan
Total Completed Inspections - 21
Date Description Inspector Results Comments
06/12/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to the main sewer line and under a water test with no leaks. Okay to shade pipes and backfill trenches.
06/12/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to the main sewer line and under a water test with no leaks. Okay to shade pipes and backfill trenches.
06/12/2024 COT - RSPL - Yard Water Line Passed Main water line is installed in trench from meter location to house and is under 60# of air pressure with no apparent leaks. Water meter has not been installed yet. Okay to proceed with shading pipe and backfilling trench.
06/18/2024 COT - RSEL - Electrical Underground Passed
06/21/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
06/21/2024 COT - RSBU - Preslab Passed
07/01/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Exterior walls are properly secured to concrete floor with shot pins, a/b bolts, and masa clips. Shear wall is properly secured per the plan. Okay to proceed with plumbing, mechanical, and electrical rough-in.
07/01/2024 COT - RSBU - Roof Nailing Passed Roof trusses are properly nailed and secured to the top plate with nails and H2.5 clips nailed per code. Roof sheathing is properly nailed to trusses per code and plans.
07/25/2024 COT - RSPL - Gas Pressure Test Passed
07/25/2024 BULD - Electrical Clearance Passed TEP ECO
07/26/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 7/26/24: DWV is under test, PEX water lines are under water pressure test, tub and shower is under water test, and penetrations in vapor barrier are sealed.
07/26/2024 COT - RSEL - Grounding/Bonding Passed
08/09/2024 COT - RSBU - Interior Shear Bracing Passed
09/19/2024 COT - BULD - SWG Clearance Passed SWG for meter only
09/24/2024 COT - RSEL - Electrical Final Passed PASSED BUILDING FINAL 9/24/24
CLEARANCE DGC
09/24/2024 COT - RSEL - Outdoor Lighting Passed PASSED BUILDING FINAL 9/24/24
09/24/2024 COT - RSME - Mechanical Final Passed PASSED BUILDING FINAL 9/24/24
09/24/2024 COT - RSPL - Plumbing Final Passed PASSED BUILDING FINAL 9/24/24
CLEARANCE DGC
09/24/2024 RSBU - Building Final Passed PASSED BUILDING FINAL 9/24/24
09/24/2024 RSBU - Building Progress Passed PASSED BUILDING FINAL 9/24/24
09/26/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
CDC 11 SIC-2024-09-13_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 11 SIC-2024-04-18_V1.PDF DOCUMENTS VIEW
CONS-CDC 11 D1_V1.PDF DOCUMENTS VIEW