Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00406
Permit Details
Apply Date:
04/05/2024
Applicant:
Cindy Nemo
Description:
Blackhawk - T698 - Layla
Permit Reviews
Permit Number - TC-MDP-0424-00406
Permit Status: Inspections complete
Permit Description: Blackhawk - T698 - Layla
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/05/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00406
Permit Status: Inspections complete
Permit Description: Blackhawk - T698 - Layla
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
04/05/2024 | Post-Tension Inspection Report is required. |
04/05/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/11/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
04/11/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/11/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0424-00406
Permit Status: Inspections complete
Permit Description: Blackhawk - T698 - Layla
Date | Description | Comments |
---|---|---|
04/11/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
04/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/11/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00406
Permit Description: Blackhawk - T698 - Layla
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/05/2024 | COT - RSPL - Backwater Valve | Passed | ||
06/05/2024 | COT - RSPL - Sewer | Passed | ||
06/05/2024 | COT - RSPL - Rough Soil | Passed | ||
06/14/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
07/05/2024 | COT - RSBU - Preslab | Passed | Approved per Ricky Ordóñez. 7/5/2024 | |
07/05/2024 | COT - RSEL - Electrical Underground | Passed | ||
07/11/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/11/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/18/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 9/18/2024 | |
09/18/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
09/18/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
09/24/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/24/2024 | |
09/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 9/24/2024 | |
10/11/2024 | COT - RSBU - Interior Shear Bracing | Passed | 10/11/24 PASS | |
11/06/2024 | RSBU - Building Progress | Passed | 11-6-24, okay to pour entryway. | |
12/03/2024 | ENGR Engineering Final | Passed | CO Ready | |
12/13/2024 | COT - BULD - SWG Clearance | Passed | PASSED SWG CLEARANCE12/13/24 | |
12/13/2024 | COT - RSEL - Electrical Final | Passed | Passed final 12/13/24 CLEARANCE ECO |
|
12/13/2024 | COT - RSEL - Outdoor Lighting | Passed | Passed final 12/13/24 | |
12/13/2024 | COT - RSME - Mechanical Final | Passed | Passed final 12/13/24 | |
12/13/2024 | COT - RSPL - Plumbing Final | Passed | Passed final 12/13/24 | |
12/18/2024 | RSBU - Building Final | Passed | Passed final 12/18/24 |