Permit: TC-MDP-0323-00805
Permit Details
Apply Date:
07/19/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2685-228 T22-M0012
Permit Reviews
Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/22/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 07/30/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
07/29/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
07/29/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
07/29/2024 | Post-Tension Inspection Report is required. |
07/29/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Date | Description | Comments |
---|---|---|
03/22/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00805
Permit Description: SFR BT2685-228 T22-M0012
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2024 | COT - RSPL - Rough Soil | Passed | ||
08/09/2024 | COT - RSPL - Sewer | Passed | ||
08/09/2024 | COT - RSPL - Yard Water Line | Passed | ||
08/16/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab. | |
08/16/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab. | |
08/16/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab. | |
09/18/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
09/18/2024 | COT - RSBU - Roof Nailing | Passed | ||
10/23/2024 | COT - RSEL - Grounding/Bonding | Passed | 10-23-24: bond wires are connected to gas lines and Ufer ground. okay to proceed. | |
10/23/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 12# of air pressure with no leaks. Okay to proceed. | |
10/25/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10/25/24: items noted on last inspection have been corrected. Okay to proceed with installation of insulation and drywall. | |
11/18/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-18-24, verified as per approved plans. Okay to tape & texture. | |
01/07/2025 | BULD - Electrical Clearance | Passed | 01/06/25 TEP Clearance code: ECO |
|
01/13/2025 | COT - BULD - SWG Clearance | Passed | Gas valves are installed at each gas appliance location. Okay to install meter. SWG Clearance issued for 9120 E. White Bluff Ct. | |
02/03/2025 | COT - RSEL - Electrical Final | Passed | 2/3/25 pass | |
02/03/2025 | COT - RSEL - Outdoor Lighting | Passed | 2/3/25 pass | |
02/03/2025 | COT - RSME - Mechanical Final | Passed | 2/3/25 pass | |
02/03/2025 | COT - RSPL - Plumbing Final | Passed | 2/3/25 pass | |
02/03/2025 | ENGR Engineering Final | Passed | CO Ready Set gate and cleanup grade on left side |
|
02/03/2025 | RSBU - Building Final | Passed | 2/3/25 pass | |
02/03/2025 | RSBU - Building Progress | Passed | 2/3/25 pass |