Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
07/19/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2685-228 T22-M0012

Permit Reviews

Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Start Date Submittal Complete Date Status  
07/22/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/30/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Total Outstanding Activity Conditions - 4
Date Name
07/29/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/29/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/29/2024 Post-Tension Inspection Report is required.
07/29/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0323-00805
Permit Status: Inspections complete
Permit Description: SFR BT2685-228 T22-M0012
Date Description Comments
03/22/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00805
Permit Description: SFR BT2685-228 T22-M0012
Total Completed Inspections - 21
Date Description Inspector Results Comments
08/09/2024 COT - RSPL - Rough Soil Passed
08/09/2024 COT - RSPL - Sewer Passed
08/09/2024 COT - RSPL - Yard Water Line Passed
08/16/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab.
08/16/2024 COT - RSBU - Preslab Passed Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab.
08/16/2024 COT - RSEL - Electrical Underground Passed Concrete forms are set, post tension cabling is evenly spaced, masa clips are evenly spaced and secured to concrete forms, shear wall straps are properly placed to plan requirements and secured to the concrete forms, all underground plumbing pipes are properly wrapped with foam, underground electrical conduit is installed for kitchen island, additional rebar reinforcement is installed per plan, and 20' rebar is properly installed for Ufer ground. Okay to pour concrete for footings and slab.
09/18/2024 COT - RSBU - Exterior Clips/Sheathing Passed
09/18/2024 COT - RSBU - Roof Nailing Passed
10/23/2024 COT - RSEL - Grounding/Bonding Passed 10-23-24: bond wires are connected to gas lines and Ufer ground. okay to proceed.
10/23/2024 COT - RSPL - Gas Pressure Test Passed Gas line is holding 12# of air pressure with no leaks. Okay to proceed.
10/25/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 10/25/24: items noted on last inspection have been corrected. Okay to proceed with installation of insulation and drywall.
11/18/2024 COT - RSBU - Interior Shear Bracing Passed 11-18-24, verified as per approved plans. Okay to tape & texture.
01/07/2025 BULD - Electrical Clearance Passed 01/06/25
TEP Clearance code: ECO
01/13/2025 COT - BULD - SWG Clearance Passed Gas valves are installed at each gas appliance location. Okay to install meter. SWG Clearance issued for 9120 E. White Bluff Ct.
02/03/2025 COT - RSEL - Electrical Final Passed 2/3/25 pass
02/03/2025 COT - RSEL - Outdoor Lighting Passed 2/3/25 pass
02/03/2025 COT - RSME - Mechanical Final Passed 2/3/25 pass
02/03/2025 COT - RSPL - Plumbing Final Passed 2/3/25 pass
02/03/2025 ENGR Engineering Final Passed CO Ready
Set gate and cleanup grade on left side
02/03/2025 RSBU - Building Final Passed 2/3/25 pass
02/03/2025 RSBU - Building Progress Passed 2/3/25 pass

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 3 - LOT 11 START_V1.PDF DOCUMENTS VIEW
BTIII 11 SIC-2024-07-19_V1.PDF DOCUMENTS VIEW