Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
12/19/2023
Applicant:
Celina Rodriguez
Description:
SFR BT1262-130 T22-M0016

Permit Reviews

Permit Number - TC-MDP-0323-00654
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
Start Date Submittal Complete Date Status  
12/20/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 12/29/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0323-00654
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
Total Outstanding Activity Conditions - 5
Date Name
12/20/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/20/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
12/20/2023 Post-Installed Anchor Inspection Report is required.
12/20/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
12/21/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0323-00654
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
Date Description Comments
12/20/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0323-00654
Permit Description: SFR BT1262-130 T22-M0016
Total Completed Inspections - 21
Date Description Inspector Results Comments
01/08/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to main sewer line and under a water pressure test with no leaks present. Okay to shade pipes and backfill trenches.
01/08/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to main sewer line and under a water pressure test with no leaks present. Okay to shade pipes and backfill trenches.
01/12/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Rebar reinforcement is in place as required by plans, post tension cabling is properly supported off the ground, footing are properly dug for shear wall clips, setbacks are correct per plan, and all plumbing pipes and tub/shower pipes are properly protected from damage due to concrete. Okay to pour slab and footings.
01/12/2024 COT - RSEL - Grounding/Bonding Passed Ufer ground is a 20' piece of rebar reinforcement in the bottom of footer.
01/12/2024 COT - RSBU - Preslab Passed Rebar reinforcement is in place as required by plans, post tension cabling is properly supported off the ground, footing are properly dug for shear wall clips, setbacks are correct per plan, and all plumbing pipes and tub/shower pipes are properly protected from damage due to concrete. Okay to pour slab and footings.
01/12/2024 COT - RSEL - Electrical Underground Passed Underground electrical for kitchen island is in place. Okay to pour concrete slab and footings.
02/02/2024 COT - RSPL - Yard Water Line Passed
02/05/2024 COT - RSBU - Exterior Clips/Sheathing Passed 2/5/24: all corrections made
02/05/2024 COT - RSBU - Roof Nailing Passed 2/5/24: all corrections made
03/01/2024 BULD - Electrical Clearance Passed TEP eco
03/12/2024 COT - RSPL - Gas Pressure Test Passed
03/13/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 3/13/24: DWV piping is under a water test with no leaks. Okay to proceed with installation of insulation and drywall.
04/03/2024 COT - RSBU - Interior Shear Bracing Passed
05/23/2024 COT - BULD - SWG Clearance Passed SWG for meter only
06/11/2024 COT - RSEL - Electrical Final Passed
06/11/2024 COT - RSEL - Outdoor Lighting Passed
06/11/2024 COT - RSME - Mechanical Final Passed
06/11/2024 COT - RSPL - Plumbing Final Passed
06/11/2024 ENGR Engineering Final Passed
06/11/2024 RSBU - Building Progress Passed
06/11/2024 RSBU - Building Final Passed