Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
02/28/2024
Applicant:
Paul Schmidt
Description:
SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)

Permit Reviews

Permit Number - TC-MDP-0224-00259
Permit Status: Inspections complete
Permit Description: SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)
Start Date Submittal Complete Date Status  
03/01/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 03/15/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0224-00259
Permit Status: Inspections complete
Permit Description: SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)
Total Outstanding Activity Conditions - 7
Date Name
02/27/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
02/27/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
03/15/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
03/15/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/15/2024 Post-Installed Anchor Inspection Report is required.
03/15/2024 Post-Tension Inspection Report is required.
03/15/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Conditions

Permit Number - TC-MDP-0224-00259
Permit Status: Inspections complete
Permit Description: SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)
Date Description Comments
02/27/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
03/15/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00259
Permite Description: SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
10/04/2024 COT - RSEL - Electrical Final N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 COT - RSEL - Outdoor Lighting N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 COT - RSME - Mechanical Final N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 COT - RSPL - Plumbing Final N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 RSBU - Building Final N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED
10/04/2024 RSBU - Building Progress N/A Re-inspection required 10/4/24: cut clean outs to grade and UV coat, exterior plastic piping must be UV Coated, post tension tag required at hose bib, AC units are being over amped, please provide approved plans at final, b-vent at water heater requires tape at single wall pipe, listing at garage must be clear, light fixtures missing throughout house. No ladder for attic access.STOPPED INSPECTION MORE ITEMS MAY BE ADDED

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00259
Permit Description: SFR F40J22 T22-M0022 revision truss calcs (optional GR RM added)
Total Completed Inspections - 23
Date Description Inspector Results Comments
04/23/2024 COT - RSPL - Rough Soil Passed
04/23/2024 COT - RSPL - Sewer Passed
04/23/2024 COT - RSPL - Yard Water Line Passed
05/01/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, post tension cabling is properly installed and spaced, required rebar reinforcement is in place per plans, all plumbing pipes are properly wrapped for protection, underground electrical for kitchen island and floor outlet in great room is installed, Ufer ground rebar is installed. Okay to pour concrete for footings and slab.
05/01/2024 COT - RSBU - Preslab Passed Concrete forms are set, post tension cabling is properly installed and spaced, required rebar reinforcement is in place per plans, all plumbing pipes are properly wrapped for protection, underground electrical for kitchen island and floor outlet in great room is installed, Ufer ground rebar is installed. Okay to pour concrete for footings and slab.
05/01/2024 COT - RSEL - Electrical Underground Passed Concrete forms are set, post tension cabling is properly installed and spaced, required rebar reinforcement is in place per plans, all plumbing pipes are properly wrapped for protection, underground electrical for kitchen island and floor outlet in great room is installed, Ufer ground rebar is installed. Okay to pour concrete for footings and slab.
05/01/2024 COT - RSEL - Grounding/Bonding Passed Concrete forms are set, post tension cabling is properly installed and spaced, required rebar reinforcement is in place per plans, all plumbing pipes are properly wrapped for protection, underground electrical for kitchen island and floor outlet in great room is installed, Ufer ground rebar is installed. Okay to pour concrete for footings and slab.
05/01/2024 COT - RSPL - Backwater Valve Passed Backwater valve is installed between clean outs. Okay to proceed.
06/03/2024 COT - RSBU - Roof Nailing Passed
06/04/2024 COT - RSBU - Exterior Clips/Sheathing Passed
07/11/2024 COT - RSPL - Gas Pressure Test Passed
07/12/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 7/12/24: All rips, tears, and holes in vapor barrier have been sealed with foam or caulking. Okay to proceed with insulation and drywall installation.
07/29/2024 COT - RSBU - Interior Shear Bracing Passed Drywall on interior shear walls is properly installed and secured to the studs per plan requirements. Okay to proceed with drywall tape, texture, and paint.
09/19/2024 COT - BULD - SWG Clearance Passed SWG for meter connection
09/20/2024 BULD - Electrical Clearance Passed TEP ECO
10/04/2024 COT - FCON - Sprinkler - Final Passed
10/04/2024 ENGR Engineering Final Passed CO Ready
10/11/2024 COT - RSEL - Electrical Final Passed 10/11/24: All noted items have been corrected. Construction is complete per plans. Okay to issue Certificate of Occupancy.
10/11/2024 COT - RSEL - Outdoor Lighting Passed Construction is complete per plans. Okay to issue Certificate of Occupancy.
10/11/2024 COT - RSME - Mechanical Final Passed 10/11/24: All noted items have been corrected. Construction is complete per plans. Okay to issue Certificate of Occupancy.
10/11/2024 COT - RSPL - Plumbing Final Passed 10/11/24: All noted items have been corrected. Construction is complete per plans. Okay to issue Certificate of Occupancy.
10/11/2024 RSBU - Building Final Passed 10/11/24: All noted items have been corrected. Construction is complete per plans. Okay to issue Certificate of Occupancy.
10/11/2024 RSBU - Building Progress Passed 10/11/24: All noted items have been corrected. Construction is complete per plans. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT.-2024-02-28_V1.PDF DOCUMENTS VIEW