Permit: TC-MDP-0224-00165
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6733 E VIA DE AYATE
Address NEW:
6733 E VIA DE AYATE
Apply Date:
05/16/2024
Applicant:
Craig Morczynski
Description:
SFR LENNLE4002 T22-M0046
Permit Reviews
Permit Number - TC-MDP-0224-00165
Permit Status: Inspections complete
Permit Description: SFR LENNLE4002 T22-M0046
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/16/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/22/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0224-00165
Permit Status: Inspections complete
Permit Description: SFR LENNLE4002 T22-M0046
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 02/05/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 05/16/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 05/16/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 05/16/2024 | Post-Tension Inspection Report is required. |
| 05/16/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 07/14/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0224-00165
Permit Status: Inspections complete
Permit Description: SFR LENNLE4002 T22-M0046
| Date | Description | Comments |
|---|---|---|
| 02/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/16/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00165
Permite Description: SFR LENNLE4002 T22-M0046
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/08/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | Partial pass. Revision will be sent in to match electrical plans at final. Okay to proceed at own risk. 10/8/2024 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00165
Permit Description: SFR LENNLE4002 T22-M0046
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2024 | COT - RSPL - Rough Soil | Passed | ||
| 06/13/2024 | COT - RSPL - Sewer | Passed | ||
| 06/13/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 06/24/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 06/24/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 06/26/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 06/26/2024 | COT - RSBU - Preslab | Passed | ||
| 08/08/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Corrections were made. 8/8/2024 | |
| 08/08/2024 | COT - RSBU - Roof Nailing | Passed | Corrections were made. 8/8/2024 | |
| 09/26/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/26/2024 | |
| 09/26/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 09/26/2024 | RSBU - Building Progress | Passed | ||
| 10/15/2024 | COT - RSBU - Interior Shear Bracing | Passed | PASSED INTERIOR SHEAR WALL BRACING 10/15/24 | |
| 12/13/2024 | COT - BULD - SWG Clearance | Passed | PASSED SW GAS CLEARANCE 12/13/24 | |
| 12/13/2024 | COT - RSPL - Plumbing Final | Passed | Per plans 12/13/24 | |
| 01/13/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Passed final 1/13/25 | |
| 01/13/2025 | COT - RSEL - Electrical Final | Passed | Passed final 1/13/25 CLEARANCE ECO | |
| 01/13/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 1/13/25 | |
| 01/13/2025 | COT - RSME - Mechanical Final | Passed | Passed final 1/13/25 | |
| 01/13/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 01/13/2025 | RSBU - Building Final | Passed | Passed final 1/13/25 |