Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0224-00162
Permit Details
Apply Date:
02/05/2024
Applicant:
Craig Morczynski
Description:
SFR LENNLE4001 T22-M0045
Permit Reviews
Permit Number - TC-MDP-0224-00162
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/08/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 03/21/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0224-00162
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
02/05/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
03/20/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
03/20/2024 | Post-Installed Anchor Inspection Report is required. |
03/20/2024 | Post-Tension Inspection Report is required. |
03/20/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
07/18/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0224-00162
Permit Status: Inspections complete
Permit Description: SFR LENNLE4001 T22-M0045
Date | Description | Comments |
---|---|---|
02/05/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/18/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/20/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00162
Permite Description: SFR LENNLE4001 T22-M0045
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/03/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | Canceled per contractor. 9/3/2024 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0224-00162
Permit Description: SFR LENNLE4001 T22-M0045
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/16/2024 | COT - RSPL - Rough Soil | Passed | ||
05/16/2024 | COT - RSPL - Sewer | Passed | ||
05/16/2024 | COT - RSPL - Yard Water Line | Passed | ||
05/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
05/23/2024 | COT - RSBU - Preslab | Passed | ||
05/23/2024 | COT - RSEL - Electrical Underground | Passed | ||
05/23/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
07/15/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Corrections were made. 7/15/2024 | |
07/15/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/03/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
09/03/2024 | RSBU - Building Progress | Passed | ||
09/05/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/5/2024 | |
09/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Approved. 9/5/2024 | |
09/13/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
11/06/2024 | COT - BULD - SWG Clearance | Passed | 11-6-24, approved for Southwest gas connection. All shutoff valves in place. | |
11/19/2024 | RSBU - Building Final | Passed | 11-19-24, electrical, plumbing, outdoor lighting, mechanical, and building final approved. | |
11/19/2024 | ENGR Engineering Final | Passed | CO Ready | |
11/19/2024 | COT - RSPL - Plumbing Final | Passed | 11-19-24, electrical, plumbing, outdoor lighting, mechanical, and building final approved. | |
11/19/2024 | COT - RSME - Mechanical Final | Passed | 11-19-24, electrical, plumbing, outdoor lighting, mechanical, and building final approved. | |
11/19/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-19-24, electrical, plumbing, outdoor lighting, mechanical, and building final approved. | |
11/19/2024 | COT - RSEL - Electrical Final | Passed | 11-19-24, electrical, plumbing, outdoor lighting, mechanical, and building final approved. |