Permit: TC-MDP-0126-00024
Permit Details
Status:
Inspections
Type:
Model Building Permit
Address:
10017 E LEBARON DR
Address NEW:
10017 E LEBARON DR
Apply Date:
02/02/2026
Applicant:
Celina Rodriguez
Description:
Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
Permit Reviews
Permit Number - TC-MDP-0126-00024
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2026 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/13/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0126-00024
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/28/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 01/28/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 01/28/2026 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 02/10/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 02/10/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0126-00024
Permit Status: Inspections
Permit Description: Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
| Date | Description | Comments |
|---|---|---|
| 01/28/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/28/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0126-00024
Permite Description: Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2026 | COT - RSPL - Sewer | N/A | Not Ready | 03/03/2026 Not under water test. |
| 03/03/2026 | COT - RSPL - Rough Soil | N/A | Not Ready | 03/03/2026 Not under water test. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0126-00024
Permit Description: Mirador Ridge Blossom 1728 Plan (Model master plan TC-MDP-0725-00411)
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2026 | COT - RSPL - Yard Water Line | Passed | 03/05/2026 Holding under test. Okay to backfill with shading. |
|
| 03/11/2026 | COT - RSBU - Preslab | Passed | 03/11/2026 Approved site plan, rebar reinforcement and foundation details - ok for concrete placement. |
|
| 03/11/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 03/11/2026 Approved site plan, rebar reinforcement and foundation details - ok for concrete placement. |
|
| 03/11/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 03/27/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 3.27.26 Truss report on site proceed |
|
| 03/27/2026 | COT - RSBU - Roof Nailing | Passed | 3.27.26 Truss report on site proceed |
|
| 04/02/2026 | BULD - Electrical Clearance | Passed | 4.2.26 Approved for eco clearance |