Permit: TC-MDP-0126-00016
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
9993 E LEBARON DR
Address NEW:
9993 E LEBARON DR
Apply Date:
02/02/2026
Applicant:
Celina Rodriguez
Description:
Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Permit Reviews
Permit Number - TC-MDP-0126-00016
Permit Status: Inspections complete
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/27/2026 | SPECIAL INSPECTION REVIEW v.2 | 07/28/2026 | APPROVED |
| 07/27/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/27/2026 | REQUIRES RESUBMIT |
| 02/05/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 02/13/2026 | APPROVED |
Conditions
Permit Number - TC-MDP-0126-00016
Permit Status: Inspections complete
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
| Date | Description | Comments |
|---|---|---|
| 01/14/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. | |
| 02/10/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 01/14/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/14/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/14/2026 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 01/14/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0126-00016
Permite Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/24/2026 | RSBU - Building Final | N/A | Partial Pass | Partial pass. Correction was made. Pending unsatisfied conditions. 7/24/2026 |
| 07/21/2026 | ENGR Engineering Final | N/A | Not Ready | 7/21/26 Outstanding condition needs to be satisfied before final inspections. -Air leakage and duct tightness. -Sewer release -concrete installation -post tension slab |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0126-00016
Permit Description: Mirador Ridge Blossom 2685 Plan (Model master plan TC-MDP-0725-00414)
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2026 | COT - RSPL - Yard Water Line | Passed | 03/06/2026 Holding under air test with blue tracer wire in clean trench - ok to backfill with shading material. |
|
| 03/06/2026 | COT - RSPL - Rough Soil | Passed | 03/06/2026 All fixtures present and under test with proper directional flow in clean trench - ok to backfill with shading material. |
|
| 03/17/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 3/17/2026 Approved per site plan and reinforcement. Ok to pour. |
|
| 03/17/2026 | COT - RSBU - Preslab | Passed | 3/17/2026 Approved per site plan and reinforcement. Ok to pour. |
|
| 03/17/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 04/08/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 04/08/2026 Corrections made to prior inspection. Verified truss calcs and bracing. |
|
| 04/08/2026 | COT - RSBU - Roof Nailing | Passed | 04/08/2026 Corrections made to prior inspection. Verified truss calcs and bracing. |
|
| 05/12/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/12/2026 | BULD - Electrical Clearance | Passed | Approved for eco | |
| 05/12/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/27/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 06/22/2026 | COT - RSPL - Sewer | Passed | ||
| 07/15/2026 | COT - BULD - SWG Clearance | Passed | 7-15-26 SWG Clearance Approved | |
| 07/21/2026 | RSBU - Building Progress | Passed | ||
| 07/21/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 07/21/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/23/2026 | COT - RSEL - Electrical Final | Passed | ||
| 07/23/2026 | COT - RSME - Mechanical Final | Passed | ||
| 07/27/2026 | RSBU - Building Final | Passed | ||
| 07/27/2026 | ENGR Engineering Final | Passed |