Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
3241 S CAPRI CI UNIT 1
Apply Date:
01/05/2026
Applicant:
Ramon VALDEZ
Description:
Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)

Permit Reviews

Permit Number - TC-MDP-0126-00001
Permit Status: Inspections complete
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Start Date Submittal Complete Date Status  
01/14/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 01/30/2026 REQUIRES RESUBMIT Review Details
02/19/2026 ADMINISTRATIVE v.1 02/19/2026 REQUIRES RESUBMIT Review Details
03/02/2026 ADMINISTRATIVE v.2 N/A APPROVED Review Details
02/05/2026 SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 02/19/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0126-00001
Permit Status: Inspections complete
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Outstanding Activity Conditions - 1
Date Name
01/06/2026 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.

Conditions

Permit Number - TC-MDP-0126-00001
Permit Status: Inspections complete
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Date Description Comments
01/06/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
01/06/2026 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
01/06/2026 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0126-00001
Permite Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
05/07/2026 COT - BULD - SWG Clearance N/A Not Applicable
05/07/2026 COT - RSEL - Electrical Underground N/A Not Applicable
05/07/2026 COT - RSPL - Gas Pressure Test N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0126-00001
Permit Description: Duplex SFR & ADU (Model master plan TC-MDP-1224-01416)
Total Completed Inspections - 17
Date Description Inspector Results Comments
03/03/2026 COT - RSPL - Rough Soil Passed Okay to backfill. Shading required. 3/3/2026
03/03/2026 COT - RSPL - Sewer Passed Okay to backfill. Shading required. 3/3/2026
03/03/2026 COT - RSPL - Yard Water Line Passed Okay to backfill. Shading required. 3/3/2026
03/06/2026 COT - RSBU - Preslab Passed 3/6/2026 string line was in place to verify proper line as the current fence is at a curb. All other corrections were made. Okay for concrete placement.
03/06/2026 COT - RSBU - Excavation/Rebar/Zoning Passed 3/6/2026 string line was in place to verify proper line as the current fence is at a curb. All other corrections were made. Okay for concrete placement.
03/31/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
03/31/2026 COT - RSBU - Roof Nailing Passed
04/03/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 4-3-26: residential intermediates approved.
04/03/2026 BULD - Electrical Clearance Passed 4-3-26: okay to energize panel at unit's 1& 2. ECO clearance issued to TEP.
05/07/2026 COT - RSBU - Interior Shear Bracing Passed
05/07/2026 COT - RSEL - Electrical Final Passed
05/07/2026 COT - RSEL - Outdoor Lighting Passed
05/07/2026 COT - RSME - Mechanical Final Passed
05/07/2026 COT - RSPL - Plumbing Final Passed
05/07/2026 ENGR Engineering Final Passed
05/07/2026 RSBU - Building Final Passed
05/07/2026 RSBU - Building Progress Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CAPRI RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
CONS-CAPRI CORRECTED_V2.PDF DOCUMENTS VIEW