Permit: TC-MDP-0125-00028
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
7352 S AVENIDA OBELO
Address NEW:
7352 S AVENIDA OBELO
Apply Date:
01/28/2025
Applicant:
Brianna Quiroz
Description:
Roosevelt Model SFR La Estancia (Model master plan TC-MDP-0123-00366)
Permit Reviews
Permit Number - TC-MDP-0125-00028
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia (Model master plan TC-MDP-0123-00366)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2025 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 02/06/2025 | APPROVED |
| 10/07/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/07/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0125-00028
Permit Status: Complete
Permit Description: Roosevelt Model SFR La Estancia (Model master plan TC-MDP-0123-00366)
| Date | Description | Comments |
|---|---|---|
| 01/17/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 01/31/2025 | Post-Installed Anchor Inspection Report is required. | |
| 01/31/2025 | Post-Tension Inspection Report is required. | |
| 01/17/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 01/17/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 01/31/2025 | Soils Testing Special Inspection is Required. | |
| 10/07/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0125-00028
Permite Description: Roosevelt Model SFR La Estancia (Model master plan TC-MDP-0123-00366)
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 05/06/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 05/28/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | 5-28-25, missing nails north side sheathing of garage. Add nails to marked areas. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0125-00028
Permit Description: Roosevelt Model SFR La Estancia (Model master plan TC-MDP-0123-00366)
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 05/06/2025 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 5/6/2025 | |
| 05/06/2025 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 5/6/2025 | |
| 05/06/2025 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 5/6/2025 | |
| 05/08/2025 | COT - RSBU - Preslab | Passed | ||
| 05/08/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 05/28/2025 | COT - RSBU - Roof Nailing | Passed | 5-28-25, roof nailing approved. | |
| 06/26/2025 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 6/26/2025 | |
| 06/26/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/02/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 7/2/25 fha plates added to dining room truss and second floor | |
| 07/10/2025 | COT - RSBU - Interior Shear Bracing | Passed | 7-10-25: interior shear wall approved okay for tape & texture. | |
| 10/20/2025 | COT - RSEL - Electrical Final | Passed | 10.20.2025 Add brace to disconnect whip near AC condenser, marked heat kit at air handler label. Correct same day, verified. |
|
| 10/20/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 10/20/2025 | COT - RSME - Mechanical Final | Passed | 10.20.2025 Add brace to disconnect whip near AC condenser, marked heat kit at air handler label. Correct same day, verified. |
|
| 10/20/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 10/20/2025 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. Engineering is good for CofO. | |
| 10/20/2025 | RSBU - Building Final | Passed | 10.20.2025 Add brace to disconnect whip near AC condenser, marked heat kit at air handler label. Correct same day, verified. |
|
| 10/20/2025 | RSBU - Building Progress | Passed |