Permit: TC-MDP-0124-00096
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
4341 S STONE BLUFF LN
Address NEW:
4341 S STONE BLUFF LN
Apply Date:
01/17/2024
Applicant:
Celina Rodriguez
Description:
SFR BT1262-130 T22-M0016
Permit Reviews
Permit Number - TC-MDP-0124-00096
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/18/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 01/24/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0124-00096
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 01/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 01/18/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 01/22/2024 | Post-Tension Inspection Report is required. |
| 01/22/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0124-00096
Permit Status: Inspections complete
Permit Description: SFR BT1262-130 T22-M0016
| Date | Description | Comments |
|---|---|---|
| 01/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0124-00096
Permite Description: SFR BT1262-130 T22-M0016
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 03/28/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Canceled |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0124-00096
Permit Description: SFR BT1262-130 T22-M0016
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 01/29/2024 | COT - RSPL - Rough Soil | Passed | ||
| 01/29/2024 | COT - RSPL - Sewer | Passed | ||
| 02/05/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 02/05/2024 | COT - RSBU - Preslab | Passed | ||
| 02/05/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 03/04/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 3/4/24: all corrections made | |
| 03/04/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 03/28/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 04/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 4/5/24: Missing registers and ductwork have been installed. Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
| 04/10/2024 | BULD - Electrical Clearance | Passed | TEP ECO | |
| 04/18/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 06/11/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 06/28/2024 | COT - RSEL - Electrical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled and AFCI/GFCI Breakers are installed for bedrooms, kitchen, bathrooms, laundry, exterior outlets and garage outlets. Okay to issue Certificate of Occupancy once all other inspections are completed. | |
| 06/28/2024 | COT - RSEL - Outdoor Lighting | Passed | Outdoor lighting is properly installed per plan requirements. Okay to issue Certificate of Occupancy. | |
| 06/28/2024 | COT - RSME - Mechanical Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled and AFCI/GFCI Breakers are installed for bedrooms, kitchen, bathrooms, laundry, exterior outlets and garage outlets. Okay to issue Certificate of Occupancy once all other inspections are completed. | |
| 06/28/2024 | COT - RSPL - Plumbing Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled and AFCI/GFCI Breakers are installed for bedrooms, kitchen, bathrooms, laundry, exterior outlets and garage outlets. Okay to issue Certificate of Occupancy once all other inspections are completed. | |
| 06/28/2024 | ENGR Engineering Final | Passed | ||
| 06/28/2024 | RSBU - Building Final | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled and AFCI/GFCI Breakers are installed for bedrooms, kitchen, bathrooms, laundry, exterior outlets and garage outlets. Okay to issue Certificate of Occupancy once all other inspections are completed. | |
| 06/28/2024 | RSBU - Building Progress | Passed | Construction is completed. Mechanical, electrical, and plumbing fixtures are installed and operational. Electrical panel is properly labeled and AFCI/GFCI Breakers are installed for bedrooms, kitchen, bathrooms, laundry, exterior outlets and garage outlets. Okay to issue Certificate of Occupancy once all other inspections are completed. |