Permit: TC-MDP-0124-00074
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
2760 S BRANDYWINE LN
Address NEW:
2760 S BRANDYWINE LN
Apply Date:
01/11/2024
Applicant:
Chris Irby
Description:
CS1453t (Model Master Plan TC-MDP-0723-01249)
Permit Reviews
Permit Number - TC-MDP-0124-00074
Permit Status: Complete
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/13/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/14/2025 | APPROVED |
| 03/02/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/10/2026 | APPROVED |
| 02/29/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.2 | 03/15/2024 | APPROVED |
| 09/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/24/2025 | REQUIRES RESUBMIT |
| 02/20/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/24/2026 | REQUIRES RESUBMIT |
| 01/12/2024 | SITE FROM MODEL TEMPLATE - INFILL BUILDERS v.1 | 01/26/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0124-00074
Permit Status: Complete
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
| Date | Description | Comments |
|---|---|---|
| 01/12/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/15/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 01/12/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/12/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 03/15/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/14/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 01/11/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 01/12/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 01/12/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
| 07/31/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0124-00074
Permite Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2025 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Canceled | |
| 04/28/2025 | COT - RSBU - Preslab | N/A | Canceled | |
| 05/12/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | 1-Plot plan does not include the Elevation designation. 2-Slab has voids throughout, including at hold-downs, MASA straps, and post tension tendons; provide evaluation of conditions from Engineer of Record verifying adequacy of all devices in concrete at voids. |
| 05/12/2025 | COT - RSBU - Roof Nailing | N/A | Not Ready | 1-Plot plan does not include the Elevation designation. 2-Slab has voids throughout, including at hold-downs, MASA straps, and post tension tendons; provide evaluation of conditions from Engineer of Record verifying adequacy of all devices in concrete at voids. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0124-00074
Permit Description: CS1453t (Model Master Plan TC-MDP-0723-01249)
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2025 | BULD - Electrical Clearance | Passed | 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required | |
| 04/28/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 04/28/2025 | COT - RSPL - Rough Soil | Passed | 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required | |
| 04/28/2025 | COT - RSPL - Yard Water Line | Passed | 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required | |
| 04/28/2025 | COT - RSPL - Sewer | Passed | 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required | |
| 04/28/2025 | COT - RSPL - Backwater Valve | Passed | 4/28/25: plumbing underground per plan ok to proceed with backfill, Main water line approved. Shading required | |
| 05/01/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Passed 5/1/25 ready to pour concrete | |
| 05/01/2025 | COT - RSBU - Preslab | Passed | Passed 5/1/25 ready to pour concrete | |
| 06/11/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Passed 6/11/25 | |
| 06/11/2025 | COT - RSBU - Roof Nailing | Passed | Passed 6/11/25 | |
| 06/11/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Passed 6/11/25 | |
| 06/11/2025 | COT - RSEL - Grounding/Bonding | Passed | Passed 6/10/25 | |
| 06/13/2025 | COT - RSPL - Gas Pressure Test | Passed | Held pressure | |
| 08/01/2025 | COT - RSBU - Interior Shear Bracing | Passed | 8/01/25 Passed by D.C on 7/3/25. |
|
| 08/01/2025 | COT - RSEL - Electrical Final | Passed | ||
| 08/01/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/01/2025 | COT - RSME - Mechanical Final | Passed | ||
| 08/01/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 08/01/2025 | RSBU - Building Final | Passed | ||
| 08/01/2025 | RSBU - Building Progress | Passed | ||
| 08/01/2025 | COT - BULD - SWG Clearance | Passed | 8/01/25 SOUTHWEST GAS CLEARANCE: SWG |
|
| 08/07/2025 | ENGR Engineering Final | Passed | Site is safe and accessible. Everything completed in accordance with approved plans. |