Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0124-00041
Permit Details
Apply Date:
01/13/2024
Applicant:
Daria Hopkins
Description:
SFR MER1402370 T21-M0077 REV1 roof covering change
Permit Reviews
Permit Number - TC-MDP-0124-00041
Permit Status: Complete
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/26/2024 | APPROVED |
07/22/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/23/2024 | APPROVED |
01/16/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 01/23/2024 | APPROVED |
06/14/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/17/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0124-00041
Permit Status: Complete
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change
Date | Description | Comments |
---|---|---|
01/16/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
01/16/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
01/16/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
01/16/2024 | Post-Tension Inspection Report is required. | |
01/09/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
01/09/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
07/23/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
01/16/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0124-00041
Permite Description: SFR MER1402370 T21-M0077 REV1 roof covering change
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/31/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | Add supports for gas line throughout. Secure gas line throughout. Replace fresh air intake. Elevate fresh air duct of ceiling. Add blocking to fresh air and 1st bedroom. Move smokie 3' from bathroom. Move smokie 6" away from wall in master bedroom. Pex lines need to be 12" away from any can lights. Add nail plates to electrical lines that are less than an 1"1/4. 7/31/2024 |
07/31/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | Provide WR receptacle. Missing cover for knock out at dead front. 7/31/2024 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0124-00041
Permit Description: SFR MER1402370 T21-M0077 REV1 roof covering change
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/22/2024 | COT - RSPL - Yard Water Line | Passed | Water line is connected to the main water meter and is under street pressure. Blue tracer wire is installed from meter to house. Okay to shade pipe and backfill trench. | |
05/24/2024 | COT - RSPL - Backwater Valve | Passed | 5/24/24: Underground plumbing, sewer line, and backwater valve are installed and under a water test. Okay to shade pipes and backfill trenches. | |
05/24/2024 | COT - RSPL - Rough Soil | Passed | 5/24/24: Underground plumbing, sewer line, and backwater valve are installed and under a water test. Okay to shade pipes and backfill trenches. | |
05/24/2024 | COT - RSPL - Sewer | Passed | 5/24/24: Underground plumbing, sewer line, and backwater valve are installed and under a water test. Okay to shade pipes and backfill trenches. | |
06/11/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
06/11/2024 | COT - RSBU - Preslab | Passed | ||
06/11/2024 | COT - RSEL - Electrical Underground | Passed | ||
07/05/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/05/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/16/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
07/31/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
08/01/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 8/1/2024 corrections were made. | |
08/01/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 8/1/2024 | |
08/19/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
09/30/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed throughout. SWG CLEARANCE ISSUED. | |
10/07/2024 | COT - RSEL - Electrical Final | Passed | 10-7-24,approved. | |
10/07/2024 | COT - RSEL - Outdoor Lighting | Passed | 10-7-24, approved. | |
10/07/2024 | COT - RSME - Mechanical Final | Passed | 10-7-24, inspected and approved. | |
10/07/2024 | COT - RSPL - Plumbing Final | Passed | 10-7-24,All plumbing fixtures were verified as operational and installed per plans. | |
10/07/2024 | ENGR Engineering Final | Passed | ||
10/07/2024 | RSBU - Building Final | Passed | 10-7-24,Final inspection approved. | |
10/07/2024 | RSBU - Building Progress | Passed |