Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
12/05/2022
Applicant:
CHARLES ELMER
Description:
SFR model Plan Alum 1585R

Permit Reviews

Permit Number - TC-MDP-0123-00330
Permit Status: Complete
Permit Description: SFR model Plan Alum 1585R
Start Date Submittal Complete Date Status  
03/17/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/20/2023 APPROVED Review Details
01/18/2023 RESIDENTIAL NEW DWELLING v.1 02/08/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0123-00330
Permit Status: Complete
Permit Description: SFR model Plan Alum 1585R
Total Outstanding Activity Conditions - 3
Date Name
02/02/2023 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
02/27/2023 A final elevation certificate must be completed before final inspection
02/27/2023 An intermediate elevation certificate of the formed pre-slab must be completed before the pre-slab inspection

Conditions

Permit Number - TC-MDP-0123-00330
Permit Status: Complete
Permit Description: SFR model Plan Alum 1585R
Date Description Comments
02/02/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00330
Permite Description: SFR model Plan Alum 1585R
Total Outstanding Inspections - 20
Last Inspection Date Description Inspector Results Comments
05/03/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 5-3-23: 1-The grounding electrode conductor for 1619 is spliced inside the service for 1617; This is not allowed per IRC E3610.1. 2-Window in Bedroom Four in not per approved plans. 3-Staggered stud walls need vertical fire locking at 10' maximum spacing per IRC R302.11#1.2.
07/26/2023 COT - RSME - Hydronic Piping N/A Not Applicable
07/26/2023 COT - BULD - SWG Clearance N/A Not Applicable
05/03/2023 COT - RSBU - Firewall/Fire Barrier/Firestop N/A Not Ready No access for inspection.
05/03/2023 COT - RSBU - Interior Shear Bracing N/A Not Ready No access for inspection.
07/26/2023 COT - RSBU - Masonry Pregrout N/A Not Applicable
07/26/2023 COT - RSBU - Stem Wall/Retaining Wall N/A Not Applicable
07/26/2023 COT - RSME - Mechanical Underground N/A Not Applicable
07/26/2023 COT - RSMH - Mobile/Mod Home Electrical N/A Not Applicable
07/26/2023 COT - RSMH - Mobile/Mod Home Final N/A Not Applicable
07/26/2023 COT - RSMH - Mobile/Mod Home Gas N/A Not Applicable
07/26/2023 COT - RSMH - Mobile/Mod Home Plumbing N/A Not Applicable
07/26/2023 COT - RSPL - Backwater Valve N/A Not Applicable
07/26/2023 COT - RSPL - Gas Final N/A Not Applicable
07/26/2023 COT - RSPL - Gas Pressure Test N/A Not Applicable
07/26/2023 COT - RSPL - Gas Reconnect N/A Not Applicable
07/26/2023 RSBU - Building Progress N/A Not Applicable 7/26/23: duplicate
07/26/2023 RSEL - Electrical Progress N/A Not Applicable 7/26/23: duplicate
07/26/2023 RSME - Mechanical Progress N/A Not Applicable 7/26/23: duplicate
07/26/2023 RSPL - Plumbing Progress N/A Not Applicable 7/26/23: duplicate

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0123-00330
Permit Description: SFR model Plan Alum 1585R
Total Completed Inspections - 17
Date Description Inspector Results Comments
03/02/2023 COT - RSPL - Rough Soil Passed duplicate
03/02/2023 COT - RSPL - Sewer Passed duplicate
03/02/2023 COT - RSPL - Yard Water Line Passed duplicate
03/17/2023 COT - RSBU - Preslab Passed Compaction of soil is complete, wire mesh reinforcement is in place, plumbing pipes are properly wrapped. Okay to pour concrete slab.
03/17/2023 COT - RSEL - Grounding/Bonding Passed #4 copper wire connected to 20' piece of rebar for user ground.
04/19/2023 COT - RSBU - Exterior Clips/Sheathing Passed
04/19/2023 COT - RSBU - Roof Nailing Passed
05/04/2023 BULD - Electrical Clearance Passed Approved, ECO clearance to TEP is required for the new service
05/04/2023 COT - RSEL - Electrical Underground Passed Approved underground electrical for both homes, okay to backfill progress areas
05/10/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Approved. Corrections have been made. 5/10/2023
07/26/2023 COT - RSEL - Outdoor Lighting Passed
07/26/2023 COT - RSBU - Interior Shear Bracing Passed
07/26/2023 RSBU - Building Final Passed
07/26/2023 COT - RSEL - Electrical Final Passed
07/26/2023 COT - RSME - Mechanical Final Passed
07/26/2023 COT - RSPL - Plumbing Final Passed
07/28/2023 COT - RSBU - Excavation/Rebar/Zoning Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
TRUSS CALCS 1617_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PLOT PLAN 1617_V1.PDF DOCUMENTS VIEW
DEAR CITY OF TUCSON REVIEWER_V1.PDF DOCUMENTS VIEW
GRADING PERMIT RECEIPT_V1.PDF DOCUMENTS VIEW