Permit: TC-COM-1125-02160
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
310 N COMMERCE PARK LP
Address NEW:
310 N COMMERCE PARK LP
Apply Date:
10/16/2025
Applicant:
Davis Kigin
Description:
Canopy Group 4: Structures J, K, L & M
Permit Reviews
Permit Number - TC-COM-1125-02160
Permit Status: Inspections
Permit Description: Canopy Group 4: Structures J, K, L & M
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/28/2025 | COMMERCIAL REVIEW - FULL v.1 | 12/04/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-1125-02160
Permit Status: Inspections
Permit Description: Canopy Group 4: Structures J, K, L & M
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 11/28/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/28/2025 | SPECIAL INSPECTION OF HIGH STRENGHT BOLTS IS REQUIRED. |
| 11/28/2025 | SPECIAL INSPECTION OF WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-1125-02160
Permit Status: Inspections
Permit Description: Canopy Group 4: Structures J, K, L & M
| Date | Description | Comments |
|---|---|---|
| 11/28/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/28/2025 | SPECIAL INSPECTION OF STEEL FRAMES IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-1125-02160
Permite Description: Canopy Group 4: Structures J, K, L & M
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2026 | COT - LCBU - Building Final | N/A | Re-inspection required | 1. Per detail 108, bollards are to concrete filled. The current bollards are hollow. 2. Also, lots of shading water near the middle of Canopy JKLM. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-1125-02160
Permit Description: Canopy Group 4: Structures J, K, L & M
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2026 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 09/29/2026 | COT - FCON - Fire - Final | Passed | ||
| 09/29/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 09/29/2026 | ENGR Engineering Final | Passed | ||
| 09/29/2026 | TRSP - ROW - Notice of Completion | Passed | ||
| 09/29/2026 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 09/29/2026 | COT - LCBU - Framing | Passed | ||
| 09/29/2026 | PDSD Building Division Pre-Construction Meeting | Passed | ||
| 09/29/2026 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 09/29/2026 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
| 09/29/2026 | BULD - Electrical Clearance | Passed | 9.28.26 TEP CLEARANCE: DGC |