Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - CSOL - Electrical Underground Solar Project

Date Description Inspector Results Comments
07/21/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 07/21/2026
Sch 80 conduit (3) 1" and (1) 3" complete at canopy J. Partial pass, okay to backfill.
07/22/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass
08/21/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 08/21/2026
Partial pass at main electrical gear rack on south side of building. Verified progress areas below, okay to backfill.
1. Canopy group ABC underground conduit sch 40 to group E run of ~280'. Conduits: (3) 1.25", (2) 1", (2) 3" for future EV chargers.
2. Canopy group FGHI to JKLM, sch 40 conduit run between I to J: (3) 1", (1) 3"
3. Canopy group DE at lighting intercept and column disconnect: (3) 1"
4. Group 1 and 2 run to group 4: (3) 1.25", (2) 1", (2) 3"
5. Group 4 at Panel 1: (4) 3", (2) 1"