Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2026 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | 07/21/2026 Sch 80 conduit (3) 1" and (1) 3" complete at canopy J. Partial pass, okay to backfill. |
|
| 07/22/2026 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | ||
| 08/21/2026 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | 08/21/2026 Partial pass at main electrical gear rack on south side of building. Verified progress areas below, okay to backfill. 1. Canopy group ABC underground conduit sch 40 to group E run of ~280'. Conduits: (3) 1.25", (2) 1", (2) 3" for future EV chargers. 2. Canopy group FGHI to JKLM, sch 40 conduit run between I to J: (3) 1", (1) 3" 3. Canopy group DE at lighting intercept and column disconnect: (3) 1" 4. Group 1 and 2 run to group 4: (3) 1.25", (2) 1", (2) 3" 5. Group 4 at Panel 1: (4) 3", (2) 1" |