Permit: TC-COM-1124-02169
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
990 E VALENCIA RD
Address NEW:
990 E VALENCIA RD
Apply Date:
11/12/2024
Applicant:
Cary Broschat
Description:
Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244
Permit Reviews
Permit Number - TC-COM-1124-02169
Permit Status: Complete
Permit Description: Installation of PV Solar shade canopies
488.01 KW dc / 390 KW ac
City of Tucson Project
related to DP-DEV-0824-00244
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/12/2024 | COMMERCIAL REVIEW - FULL v.1 | 12/04/2024 | APPROVED |
| 06/02/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/03/2025 | APPROVED |
Conditions
Permit Number - TC-COM-1124-02169
Permit Status: Complete
Permit Description: Installation of PV Solar shade canopies
488.01 KW dc / 390 KW ac
City of Tucson Project
related to DP-DEV-0824-00244
| Date | Description | Comments |
|---|---|---|
| 11/19/2024 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. (Pilings) | |
| 11/19/2024 | SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED. ( Steel Framing, High Strength Bolts) |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02169
Permite Description: Installation of PV Solar shade canopies
488.01 KW dc / 390 KW ac
City of Tucson Project
related to DP-DEV-0824-00244
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/10/2025 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
| 04/10/2025 | COT - CSOL - Electrical Underground Solar Project | N/A | Partial Pass | |
| 04/02/2025 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1124-02169
Permit Description: Installation of PV Solar shade canopies
488.01 KW dc / 390 KW ac
City of Tucson Project
related to DP-DEV-0824-00244
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 4-28-25, excavation for typical Schedule 40 conduits located on eastern side of fence to gear rack is approximately 150' and verified per plan-okay to backfill and encase. | |
| 05/23/2025 | COT - LCBU - Framing | Passed | ||
| 05/23/2025 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 05/23/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 05/23/2025 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 05/23/2025 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
| 05/23/2025 | BULD - Electrical Clearance | Passed | Approved (2) solar structures - DGC Clearance to TEP is required for the solar meter | |
| 05/23/2025 | COT - LCBU - Building Final | Passed | ||
| 05/23/2025 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 05/28/2025 | ENGR Engineering Final | Passed | ||
| 05/28/2025 | TRSP - ROW - Final/Close-Out | Passed |