Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
990 E VALENCIA RD
Apply Date:
11/12/2024
Applicant:
Cary Broschat
Description:
Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244

Permit Reviews

Permit Number - TC-COM-1124-02169
Permit Status: Complete
Permit Description: Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244
Start Date Submittal Complete Date Status  
11/12/2024 COMMERCIAL REVIEW - FULL v.1 12/04/2024 APPROVED Review Details
06/02/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/03/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-1124-02169
Permit Status: Complete
Permit Description: Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244
Date Description Comments
11/19/2024 SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. (Pilings)
11/19/2024 SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED. ( Steel Framing, High Strength Bolts)

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02169
Permite Description: Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
04/10/2025 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass
04/10/2025 COT - CSOL - Electrical Underground Solar Project N/A Partial Pass
04/02/2025 COT - CSOL - Grounding/Bonding Solar Project N/A Partial Pass

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-1124-02169
Permit Description: Installation of PV Solar shade canopies 488.01 KW dc / 390 KW ac City of Tucson Project related to DP-DEV-0824-00244
Total Completed Inspections - 11
Date Description Inspector Results Comments
04/28/2025 COT - LCBU - Excavation/Rebar/Zoning Passed 4-28-25, excavation for typical Schedule 40 conduits located on eastern side of fence to gear rack is approximately 150' and verified per plan-okay to backfill and encase.
05/23/2025 COT - LCBU - Framing Passed
05/23/2025 COT - CSOL - Electrical Intermediate Solar Project Passed
05/23/2025 COT - CSOL - Electrical Underground Solar Project Passed
05/23/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
05/23/2025 COT - CSOL - Outdoor Lighting Solar Project Passed
05/23/2025 BULD - Electrical Clearance Passed Approved (2) solar structures - DGC Clearance to TEP is required for the solar meter
05/23/2025 COT - LCBU - Building Final Passed
05/23/2025 COT - CSOL - Electrical Final Solar Project Passed
05/28/2025 ENGR Engineering Final Passed
05/28/2025 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
COT - MARTIN WELL - SI FINAL REPORT_SIGNED-2025-06-02_V1.PDF DOCUMENTS VIEW
COT - MARTIN WELL - WELDING SI FINAL_SIGNED-2025-06-02_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-COT - MARTIN WELL_COMBINED IFP_241112_V1.PDF DOCUMENTS VIEW
COT - MARTIN WELL - GEO REPORT_V1.PDF DOCUMENTS VIEW
COT - MARTIN WELL - SI CERT_SIGNED-2024-11-12_V1.PDF DOCUMENTS VIEW
COT - MARTIN WELL STRUCTURAL CALCS_V1.PDF DOCUMENTS VIEW