Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 04/10/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
|
| 04/28/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
4-28-25, excavation for typical Schedule 40 conduits located on eastern side of fence to gear rack is approximately 150' and verified per plan-okay to backfill and encase. |
| 05/01/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
5-1-25, verified electrical conduit for pull box and 3" conduit going from gear rack to POI. Okay to backfill and pour at progress areas. |
| 05/23/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Passed |
|